Wheatstone production delayed by six months

1st February 2016

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – First liquefied natural gas (LNG) production from the $29-billion Wheatstone project has been delayed by about six months, with first production now expected in mid-2017.

US oil and gas major Chevron reportedly told shareholders last week that the delay was caused by the slow schedule of construction of plant modules in Malaysia.

Australian oil and gas miner Woodside, which in April last year acquired a 13% interest in Wheatstone, said on Monday that impairments foreshadowed in the company’s quarterly reports had taken into account the potential for a revised schedule at the Wheatstone onshore plant.

Woodside pointed out that the Julimar project, in which it held a 65% equity interest, and which would supply gas to the Wheatstone onshore plant, remained on schedule and on budget.

Woodside also moved to placate stakeholders in the Wheatstone project, saying that delivery commitments under LNG sales agreement would be met under the revised production schedule.

Wheatstone is located 12 km west of Onslow, in Western Australia, and would consist of two LNG trains with a combined capacity of 8.9-million tonnes a year, along with a domestic gas plant.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.141 0.182s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: