Waterberg palladium project, South Africa

15th November 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Waterberg palladium project.

Location
The Waterberg project is located 85 km north of Mokopane in Limpopo, South Africa.

Project Owner/s
Platinum Group Metals (PTM) is the operator of the Waterberg project, with joint venture partners being Japanese Oil, Gas and Metals National Corporation, Hanwa, Impala Platinum Holdings (Implats) and Mnombo Wethu Consultants.

Project Description
PTM has announced positive results from an independent definitive feasibility study (DFS) on the Waterberg project. The DFS provides a clear outline of the palladium deposit and has concluded that it can be one of the largest, fully mechanised, low-cost platinum group metals mines in the world.

The project has proven and probable reserves of 187.51-million tonnes at 3.24 g/t platinum, palladium, rhodium and gold (4E) for 19.48-million 4E ounces (using a 2.5 g/t 4E cutoff).

The life-of-mine on current mineral reserves extends to 2066 and the deposit remains open at depth and on strike.

Updated measured and indicated mineral resources are estimated 242-million tonnes grading 3.38 g/t 4E ounces, and the deposit remains open on strike to the north and below an arbitrary depth cutoff of 1 250 m.

The DFS mine plan envisages production at 4.8-million tonnes of ore a year and 420 000 4E ounces a year in concentrate. The mine will initially access the orebody using two sets of twin decline tunnels, with mining by fully mechanised longhole stoping methods with paste backfill. Paste backfill allows for a high mining extraction ratio as mining can be completed next to backfilled stopes without leaving internal pillars.

Maintaining safety and reliability are key mine design criteria. As a result of the scale of the orebody, bulk mining on 20 m to 40 m sublevels with large underground equipment and conveyors for ore and waste transport will provide high efficiency.

The Waterberg project is planned to produce a sulphide concentrate at a grade that is attractive to the current operating smelters in South Africa, with no significant penalty elements. Implats holds a first right of refusal for smelter offtake and Hanwa, of Japan, holds the rights to market the final refined metal at market prices.

Potential Job Creation
The project will create about 1 100 new highly skilled jobs.

A significant investment in local training and business opportunities is part of the benefits to stakeholders, including local communities, shareholders, provincial and national governments.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $982-million and an internal rate of return of 20.7%

Capital Expenditure
Capital expenditure is estimated at $874-million, including $87-million in contingencies. Peak project funding estimated at $617-million.

Planned Start/End Date
The DFS project timeline includes a formal construction decision to be taken following the granting of the mining right, expected in the first quarter of 2020, with first production expected 3.5 years later.

The planned decline access provides for rapid and low-cost access to the shallow orebody. Under the DFS mine plan, first production is estimated in late 2023 with ramp-up to steady state by 2027.

Latest Developments
None stated.

Key Contracts and Suppliers
Stantec Consulting International and DRA Projects SA (DFS).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
PTM, tel +27 11782 2186 or email info@platinumgroupmetals.net.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

 

Showroom

ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.117 0.168s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: