Venetia Underground Project, South Africa – update

Image of Venetia Underground Project

Photo by De Beers Consolidated Mines

15th September 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Venetia Underground Project (VUP).

Location
Venetia mine, in Limpopo, South Africa.

Project Owner/s
Anglo American subsidiary De Beers Consolidated Mines.

Project Description
The Venetia mine, which officially opened on August 14, 1992, is currently the biggest producer of diamonds in South Africa.

The mine is an openpit operation; however, following shareholder approval, development work began in late 2013 to build the new underground mining operation beneath the current operating openpit. It is currently the biggest diamond mine development under way anywhere in the world.

The VUP will extend the mine life to 2047 and yield 88-million carats from about 134-million tonnes of material.

The project comprises the K01 and K02 orebodies. Both kimberlites extend below surface, enabling De Beers to mine to depths of up to 1 000 m. There are indications that K01 extends below 1 000 m, and De Beers may explore options that extend the underground operation’s life beyond 2045.

K01 – a sizeable orebody measuring 550 m x 120 m – will be responsible for the majority of production, generating an average of 3.5-million carats from about 4.5-million tonnes a year of material.

The K02 orebody – measuring 200 m x 300 m – will provide the balance, producing about one-million carats from 1.5-million tonnes to 2.5-million tonnes a year of material.

The current mining solution for the underground project will use sublevel caving to extract material from both orebodies. Further optimisation studies are being completed to determine whether the K02 orebody should be mined using a block cave mining methodology.

Underground infrastructure comprises two vertical shaft systems for personnel transport, ore transport and the routing of services, as well as lateral access to levels on the 54L, 91L and 94L stations for the services shaft, and on the 100L station for the production shaft.

The service shaft has a  completed internal diameter of 7 m and will eventually provide all the services and people transport for the underground workings, while the production shaft, also with a finished internal diameter of 7 m, will be fitted with two rock winders, each having two 24 t payload skips.

The service and production shafts will serve as downcast air intakes to the underground workings, while a decline and pit ramp will assist with early underground access for the construction of the production infrastructure for K01 and K02, which will be developed concurrently to the vertical shafts.

They will also serve as additional air intakes and logistical access points, which VUP says will mitigate the immediate requirement for the use of the shafts for ground handling.

Overall, VUP will undertake 61.5 km of initial excavations as part of the expansion project, as well as a further 177 km of excavations over the remainder of the underground life-of-mine.

Surface infrastructure, which includes change houses, a heat-tolerance testing centre, a lamp room, a proto room, a control room, winder houses, workshops, warehouses, ventilation systems and a state-of-the-art training facility, were completed in early 2021.

De Beers also plans to have Venetia operating as carbon neutral by 2030; using battery electric vehicles and installing a 60 MW solar photovoltaic plant are expected to help achieve that goal.

The ultimate sizing of the energy plant is yet to be finalised.

Potential Job Creation
The project currently employs 4 300 people, with the majority of employees living in the surrounding Musina and Blouberg communities. To date, 180 employees have successfully transitioned to underground operations without any job losses for Venetia Mine’s permanent employees.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
$2.3-billion.

Planned Start/End Date
First production was achieved in July 2023. The project is expected to ramp-up to full production from 2024 onwards.

Latest Developments
De Beers Group reported in July 2023 that it had delivered first production from underground operations at the Venetia mine.

The overall construction of the underground mine was 70% complete at the time, with construction and production ramp-up to continue over the next few years.

Key Contracts, Suppliers and Consultants
Murray & Roberts Cementation (development of underground mine); Redpath Australia (development of the underground mine with the De Beers team, working as the integrated owners team); Sandvik (intelligent loaders and trucks); and Rajant’s (network nodes, or BreadCrumbs).

Other contractors involved include Worley, BMH, BBE, ABB, Grinaker and Louwill.

Contact Details for Project Information
De Beers Group Managed Operations senior communications manager Jackie Mapiloko, tel +27 11 374 7173 or email jackie.mapiloko@debeersgroup.com.

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.11 0.163s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: