Vametco and Vanchem operations expansion, South Africa

Image of South Africa flag/map

26th August 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Vametco and Vanchem operations expansion.

Location
South Africa.

Project Owner/s
Bushveld Minerals.

Project Description
Bushveld’s Vametch and Vanchem operations are on track to achieve sustainable production of between 5 000 t/y and 5 400 t/y by the end of 2022.

Studies have been conducted to determine the optimal path to increase production at the operations to 8 000 t/y.

In Stage 1, it is proposed that a semiautogenous grinding (SAG) mill be installed at Vametco to establish a permanent and reliable supply of feedstock for both operations in anticipation of further capacity expansion.

Stage 2 will result in the refurbishment of Kiln 2 at the Vanchem plant to increase production from 2 600 t/y to between 3 600 t/y and 3 700 t/y.

Stage 3 will entail the refurbishment of Kiln 1 to increase production from between 3 600 t/y and 3 700 t/y to between 4 600 t/y and 4 800 t/y.

In Stage 4, single kiln capacity at Vametco will be increased from 2 800 t/y to 3 400 t/y; this will result in an overall increase in group production of about 7 600 t/y to 8 000 t/y.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The expansion will require capital expenditure of about $151-million.

Installation of the SAG mill will cost about $32.9-million. The refurbishment of Kiln 1 and Kiln 2 will cost $53-million and $37-million respectively.

The increase in single kiln capacity will cost about $28.2-million.

Planned Start/End Date
The installation of the SAG mill is expected to take 24 months, the refurbishment of Vanchem’s Kiln 1 and 2 from 18 to 24 months, and the increase in single kiln capacity 12 to 18 months.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
METC South Africa and MSA Group (feasibility and prefeasibility studies).

Contact Details for Project Information
Bushveld Minerals, tel +27 (0)11 268 6555 or email info@bushveldminerals.com
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.14 0.191s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: