Toro seeks govt approval to enlarge Wiluna
PERTH (miningweekly.com) – Uranium developer Toro Energy was seeking government approval to start mining operations at its Millipede and Lake Maitland deposits to further enhance the Wiluna project, in Western Australia.
The company already had the necessary federal and state government approvals in place to establish a processing facility at the Centipede deposit and to establish mining activities at the Centipede and Lake Way deposits.
At the end of January, an independent scoping study improved Wiluna’s project economics by integrating the Lake Maitland deposit into the project.
Based on mining at the four deposits, the Wiluna project was expected to have a mine life of 16 years with average production of two-million pounds of uranium oxide (U3O8) a year, for the first ten years of operation.
Total production over the life-of-mine would reach 30.2-million pounds U3O8.
“Toro’s overarching Wiluna strategy is to use one central processing plant adjacent to the Centipede deposit to reduce the regional footprint and environmental impacts by avoiding a duplication of operations and infrastructure,” said Toro MD Vanessa Guthrie on Friday.
“Accordingly, Toro is hopeful that the environmental assessment process for Millipede and Lake Maitland can be completed by mid-2016.”
Guthrie pointed out that the recently completed study provided a running start into Wiluna’s definitive feasibility study, with the results positioning the proposed A$315-million project as one of the few uranium mining projects in the world capable of bringing new production to global markets at a time when the uranium price was set to rise in the second half of the decade.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation