https://www.miningweekly.com

Tiger expects more copper from Kipoi

18th June 2013

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Copper miner Tiger Resources on Tuesday told shareholders that it would likely exceed its 2013 production target of 37 000 t of copper concentrate at its Kipoi copper project, in the Democratic Republic of Congo.

The miner has revised the production guidance for the Stage 1 heavy media separation (HMS) operation to between 41 000 t and 43 000 t for the full 2013.

Year-to-date production until the end of May reached 16 182 t of copper in concentrate, supporting a production estimate of 19 500 t for the six months to June.

Tiger noted that the Kipoi mine plan had been updated to include the recent grade-control drilling results, which would take the HMS processing operation until the end of 2014. The resultant mine model had reported an increase in copper grade, compared with the original model, and on this basis, HMS production for the six months to December had been targeted to between 21 500 t and 23 500 t.

The HMS operation would continue until the end of 2014, after the completion and ramp-up of the Stage 2 solvent extraction electrowinning plant, which would result in residues of some 6.1-million tons of material, grading 2.4% copper, being made available to start Stage 2 operations.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.167 0.206s - 112pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: