Thunderbird costs tracking to plan

14th February 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – The construction of the Thunderbird mineral sands project, in Western Australia, will be completed within the A$484-million budget, ASX-listed Sheffield Resources said on Tuesday.

Construction is over 75% complete and first delivery of mineral sands product remains on track for the first quarter of 2024.

“Thunderbird construction is advancing at a rapid pace, and we are extremely pleased by the progress made by the Kimberley Mineral Sands (KMS) team. We remain on schedule for commissioning later this year,” said Sheffield executive chairperson Bruce Griffin.

“Our forecast pre-production activities now include anticipated changes to operational mobilisation and scheduling to reduce startup risk, resulting in an anticipated cost increase. It is pleasing to note that KMS has continued to manage the capital expenditures in line with final investment decision estimates despite the inflationary environment. KMS remains extremely well positioned to complete the project comfortably within the current available funding of A$484-million.”

KMS has estimated the total direct expenditures through to commencement of operations to be A$407-million. After allowance for project financing costs, A$54-million of remaining contingency and working capital provisions are available, with a total funding requirement of A$484-million.

The two-stage Thunderbird development pathway sees the initial Stage 1 mining and processing feed rate forecast at 1 085 t/h at the wet concentrate plant (WCP), with Stage 2 doubling the WCP feed rate to 2 170 t/h targeted during Year 5 of operations.

Stage 1 and 2 of operations is estimated to produce 1.4-million tonne a year of zircon and ilmenite concentrates over an estimated 36 year life-of-mine.

Edited by Creamer Media Reporter

Comments

Latest News

State-owned groups Eskom and Transnet have impaired mining productivity with unreliable power supply and a lack of trains to move mineral exports.
BHP’s South Africa snub an indictment of ANC, DA says
Updated 25 minutes ago By: Bloomberg

Showroom

John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.051 0.09s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: