Thacker Pass lithium project, US

1st November 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Thacker Pass lithium project.

Location
The project is located in Humboldt County, Nevada, in the US.

Client
Lithium Americas.

Project Description
The project has a proven and probable reserve estimate of 179.4-million tonnes of ore, with an average grade of 3 283 parts per million lithium containing 3.1-million tonnes of lithium carbonate equivalent.

The prefeasibility study (PFS) envisages a large-scale lithium project, with a design capacity of 60 000 t/y of battery-grade lithium carbonate. Phase 1 production is estimated at 30 000 t/y, increasing to 60 000 t/y in Phase 2.

The project will be developed as an openpit mining operation using conventional continuous mining equipment.

Given the soft nature of the deposit, minimal blasting and crushing are expected.

The ore will be processed in a leaching circuit using sulphuric acid to liberate the lithium from the claystone.

Following the leaching process, the lithium-bearing solution will be purified using crystal-lisers and reagents to produce battery-grade lithium carbonate.

The mine plan contemplates mining 509.8-million tonnes of material, comprising 330.4-million tonnes of waste rock and 179.4-million tonnes of ore (delivered to plant) over a 46-year mine life.

With the reliance on sulphuric acid, the project will involve the construction of a 5 280 t/d (Phase 1 – 2 640 t/d ) conventional sulphuric acid plant site. The plant will convert molten sulphur into low-cost sulphuric acid, reducing transportation costs and providing a low-cost source of power.

Excess acid will be sold locally to large consumers in the region. In addition, the sulphuric acid plant proposes a cogeneration facility, providing enough carbon-free electricity to power the entire project, with excess power being sold to the grid.

Additional infrastructure in Phase 2 includes:

doubling the sulphuric acid capacity by building a second acid plant;

increasing capacity in ore preparation, leaching, filtration, crystallisation and reagent storage; and

construction of a rail line with service directly to the plant.

The production process is designed to use conventional and commonly available equipment, arranged to take advantage of the distinctive qualities of the high-grade ore. The process comprises a series of steps to concentrate, separate and produce battery-grade lithium carbonate.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $3.9-billion and an internal rate of return of 36.6%.

Value
Initial capital costs, including a 19% contingency, are estimated at $581-million for Phase 1 and at $478-million for Phase 2.

Duration
The PFS envisages initial Phase 1 production capacity of 30 000 t/y of battery-grade lithium carbonate starting in 2022. Phase 2 construction is projected to start in 2025, with added production entering the market by 2026.

Latest Developments
Lithium Americas is contemplating a smaller Phase 1 operation at its Thacker Pass project, with its production plan cut by one-third.

The company has started a definitive feasibility study (DFS) for a Phase 1 production capacity of 20 000 t/y of battery-quality lithium carbonate-equivalent (LCE).

This compares with the 2018 PFS’s planned Phase 1 production of 30 000 t/y at a capital cost of $581-million, as part of a larger 60 000 t/y operation that will cost $1.06-billion.

The DFS should be completed by mid-2020. A formal financing process, including a potential joint venture partner, will start next year.

The scaled back plan for Thacker Pass comes as lithium prices have crashed in recent months. Propelled by strong demand from the lithium-ion battery industry and uncertainty over future supply, prices exploded between 2016 and 2018, prompting widespread interest and investment in lithium projects. 

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Lithium Americas, email info@lithiumamericas.com.

Edited by Creamer Media Reporter

Comments

Showroom

Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.108 0.163s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: