Siviour graphite project, Australia

21st June 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Siviour graphite project.

Location
The project is located on South Australia’s Eyre Peninsula.

Project Owner/s
Renascor Resources.

Project Description
Renascor has adopted an optimised development plant for the Siviour graphite project, based on the mineral resource and reserve estimate first reported in April 2019. The project has total mineral resources estimated at 87.4-million tonnes grading

7.5% total graphitic carbon (TGC) for 6.6-million tonnes of contained graphite. Total total proven and probable reserves are estimated at 45.2-million tonnes grading 7.9% TGC for 3.6-million tonnes of contained graphite. This revised plan is based on a two-stage approach to achieve production of up to 145 000 t/y through the staged construction of two substantially similar-sized processing plants. The plan builds on the large-scale, 117 000 t/y production case considered in the Siviour prefeasibility study (PFS) completed in March 2018, by staging production through the construction of two substantially identical processing plants. Each plant will have an ore throughput capacity of 825 000 t/y to achieve a substantially similar yearly production rate as the large-scale 1.65-million-tonne-a-year processing plant considered in the large-scale case from the PFS. The project has an estimated life-of-mine of 40 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 10% discount rate, of A$435-million and an internal rate of return of 40%, with a payback of 3.7 years.

Capital Expenditure
Capital expenditure is estimated at A$108-million for Stage 1 and A$77-million in Stage 2.

Planned Start/End Date
Not stated.

Latest Developments
Renascor is completing work on the definitive feasibility study (DFS), which has adopted the operating parameters used in the optimised development plan.  Work on the DFS is advanced, with all major work programmes, including resource modelling and mining, tailings, engineering and logistic studies, at or near completion.

Key Contracts and Suppliers
Optiro (mineral resource estimate); Goudie Hall Consulting (metallurgical testwork); Optima Consulting and Contracting (mining and mine design); Wave International (process infrastructure); Groundwater Science (hydrogeology); JBS&G Australia (environmental permitting); George Wilby (logistics); Arup (desalination plant and infrastructure); and BurnVoir Corporate Finance (financial analysis).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Renascor Resources, tel +61 8 8363 6989 or email info@renascor.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.359 0.454s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: