Quebrada Blanca Phase 2 copper project, Chile

27th March 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Quebrada Blanca Phase 2 (QB2) copper project.

Location
Tarapacá region, in northern Chile.

Project Owner/s
Teck Resources has announced that it will proceed with the QB2 project and that Japan’s Sumitomo will be its 30% project partner.

Sumitomo was among the companies mooted as potential partners in the project, the others being Rio Tinto and Mitsubishi.

Sumitomo Metal Mining Co and Sumitomo Corporation will pay $1.2-billion for a 30% indirect interest in Compañia Minera Teck Quebrada Blanca, which owns the QB2 project, $800-million of which is an earn-in contribution and the balance a matching contribution.

The companies have also agreed to make supplemental payments to Teck.

Following the transaction, Teck will own 60% of QB2, Sumitomo 30% and Chilean State miner Enami 10%. Bringing on board Sumitomo significantly derisked Teck’s investment in the project.

The combination of proceeds from the transaction and the proposed project financing has reduced Teck’s share of equity contributions towards the unescalated $4.739-billion estimated capital cost of the QB2 project to $693-million, with Teck’s first contributions not required until late 2020.

The Canadian major has said that the board will consider an additional return of capital to shareholders following closing of the transaction, considering the significant reduction in QB2 funding required.

Project Description
QB2 is one of the world’s largest undeveloped copper resources.

The project proposes to develop the hypogene resource at Quebrada Blanca to increase yearly copper production and extend the mine’s production life by more than 25 years.

The project is expected to include the construction of a 140 000 t/d concentrator, tailings storage facility, concentrate pipeline, water supply pipeline, desalination plant, concentrate filtration plant and port to produce copper and molybdenum concentrates.

QB2 is expected to produce 316 400 t/y of copper equivalent for the first five years of mine life.

Potential Job Creation
About 15 000 people are working on the QB2 project with 2 000 ongoing direct and indirect jobs during operation.

All-in Sustaining Costs/All-in Costs
The project has an all-in sustaining cost of $1.38/lb of copper.

Net Present Value/Internal Rate of Return
Not stated.

Value
$4.8-billion.

Duration
Not stated.

Latest Developments
Teck Resources has suspended construction activities at the $4.8-billion QB2 project to support Chile’s efforts to limit the transmission of Covid-19.

The suspension will be for an initial two weeks, at which point Teck will reassess the status of the project.

Prior to the global outbreak of Covid-19, Teck already warned that there could be delays in the schedule of QB2, owing to permitting and social unrest.

The suspension of construction activities is effective immediately, and the workforce will demobilise in due course.

Teck has stressed that there have been no confirmed cases of Covid-19 associated with QB2 employees or contractors to date.

Key Contracts and Suppliers
None stated.

Contact Details for Project Information
Teck Resources senior communications specialist Chris Stannell, tel +1604699 4368 or email Chris.Stannell@teck.com.
Teck Resources investor relations, tel +1604699 4257 or email investors@teck.com.

 

Edited by Creamer Media Reporter

Comments

Latest News

The Collahuasi mine
China could hinder BHP’s bid to become copper’s top producer
Updated 2 hours 34 minutes ago By: Bloomberg
The Mogalakwena mine in South Africa
BHP considering improved proposal for Anglo American, sources say
Updated 2 hours 41 minutes ago By: Reuters

Showroom

SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.128 0.186s - 91pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: