Oyu Tolgoi underground production delay announced

16th October 2018

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

The $5.3-billion underground project at the Oyu Tolgoi copper/gold mine, in Mongolia, remains on schedule to be completed by 2022, but operator Rio Tinto has flagged a nine-month delay in achieving sustainable production.

Rio Tinto-owned Turquoise Hill, which holds the giant mine in a 66:34 partnership with the Mongolia government, reported on Tuesday that sustainable production would be achieved in the third quarter of 2021, rather than the previously guided start of 2021.

The nine-month schedule slip is the result of challenging ground conditions and delays in the completion of Shaft 2, production capability of which is a key enabler of increased underground development and further construction of critical underground infrastructure.

Until the completion of Shaft 2, Oyu Tolgoi would experience similar, but not increased, development rates as seen in the third quarter, Turquoise Hill stated.

The miner, which is listed on the NYSE and TSX, reported that it had started its own review of the cost and schedule forecast and the impact that it would have on the company, including the impact on cash flows and liquidity.

Meanwhile, Turquoise Hill CEO Ulf Quellmann reported that Oyu Tolgoi would likely meet the upper-end of its 2018 production guidance of 140 000 t to 155 000 t of copper in concentrate and 240 000 oz to 280 000 oz of gold.

In the third quarter, Oyu Tolgoi produced 49 400 t of copper in concentrate, 77 000 oz of gold in concentrate and 230 000 oz of silver in concentrate.

Copper production was flat compared with the second quarter, as higher grades and recoveries were partially offset by lower throughput. Gold production increased by 54% quarter-on-quarter, owing to higher grades and recoveries.

Third quarter sales volumes were impacted by torrential rain in July and August, which consequently affected Chinese road and rail availability. Third quarter sales volumes were generally lower than the previous quarter, which benefited from the sales of deferred volumes related to the first quarter of 2018’s force majeure.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/03/2024)
15th March 2024 By: Martin Creamer
Gold, hydrogen, mining boost make headlines
Gold, hydrogen, mining boost make headlines
15th March 2024
Magazine round up | 15 March 2024
Magazine round up | 15 March 2024
15th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.104 0.137s - 112pq - 2rq
Subscribe Now