https://www.miningweekly.com
Cleaning|composite|Construction|Copper|Design|Engineering|flotation|Logistics|Mining|PROJECT|rail|Resources|Road|transport|Products|Drilling|Infrastructure|Operations
Cleaning|composite|Construction|Copper|Design|Engineering|flotation|Logistics|Mining|PROJECT|rail|Resources|Road|transport|Products|Drilling|Infrastructure|Operations
cleaning|composite|construction|copper|design|engineering|flotation|logistics|mining|project|rail|resources|road|transport|products|drilling|infrastructure|operations

Orom-Cross graphite project, Uganda – update

Location map of the Orom-Cross project site

Photo by Blencowe Resources

27th January 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Orom-Cross graphite project.

Location
Uganda.

Project Owner/s
Graphite, nickel and copper developer Blencowe Resources.

Project Description
A prefeasibility study (PFS) has highlighted an exceptional long-life project that delivers considerable returns over an initial life-of-mine of 14 years.

An estimated 600 000 t/y of ore will be mined from the commissioning date and this will increase to 2.4-million tonnes a year by the time the project is fully ramped up in Year 10.

Mining will be free-dig, with no drill-and-blast required. Initial ore will come from saprolite (clay) at about 15 m to 20 m depth on average. Both deposits (Northern syncline and Camp lode) identified in the drilling programmes will be mined and a composite blend of both will be fed into the processing plant that will be built on site.

An initial 36 000 t/y of end-product will be delivered from the plant as concentrates, which will increase in two additional stages to 147 000 t/y once the mine is fully ramped up. 

Further resources, higher production volumes and an extended mine life can all be obtained at any stage by drilling additional ready-targets. This, however, is not currently considered a priority.

The processing flowsheet comprises a flash and rougher flotation stage, followed by a primary cleaning circuit with a polishing mill and three stages of cleaner flotation. The intermediate concentrate is classified and then further upgraded in secondary cleaning circuits with stirred media mills, followed by cleaner flotation.

Orom-Cross will deliver at least five different end-products, characterised by size fractions of +50 mesh, + 80 mesh, +100 mesh, +150 mesh and -100 mesh. These products will have different markets and will be branded and packaged at site.

Initially, transport to port will be by road, but it is expected that a rail option might be available nearby by 2025, further reducing logistics costs.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $482-million and an internal rate of return of 50%.

Capital Expenditure
The initial capital requirement has been lowered by 23% to $62-million since the preliminary economic assessment was announced in 2021. 

Planned Start/End Date
Blencowe will start the main operations from 2025 at an initial output of 36 000 t/y of end-product.

Latest Developments
Blencowe Resources has contracted engineering firm CPC Engineering to lead, deliver and sign off on the definitive feasibility study (DFS) for the Orom-Cross graphite project.

Work contracted to CPC includes an enhancement of the process plant design, incorporating results of the various testwork programmes from SGS, IMO and the pilot plant works (Jilin/China), along with CPC’s expertise in design and construction of graphite process plants.

CPC will provide updated and enhanced capital expenditure and operational expenditure for project cost and schedule certainty, as well as updated project costs and schedule for the project’s nonprocessing infrastructure. It will also sign off on full DFS once completed to provide the third-party approval from a recognised technical firm as required to ensure project funding support.

Key Contracts, Suppliers and Consultants
Battery Limits (PFS); and IMO (technical testwork); and CPC Engineering (DFS).

Contact Details for Project Information
Blencowe Resources, tel +44 1624 681 250 or email info@blencoweresourcesplc.com.

Edited by Creamer Media Reporter

Comments

Showroom

Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 
Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.11 0.165s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: