https://www.miningweekly.com
Cleaning|Financial|flotation|Mining|PROJECT|Resources|Drilling
Cleaning|Financial|flotation|Mining|PROJECT|Resources|Drilling
cleaning|financial|flotation|mining|project|resources|drilling

Orom-Cross graphite project, Uganda

Image of graphite ore

15th October 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Orom-Cross graphite project.

Location
Uganda.

Project Owner/s
Blencowe Resources.

Project Description
A preliminary economic assessment has shown the potential of Orom-Cross to deliver a long-life mining operation with strong financial returns.

The project proposes the development of an openpit, owner-operated mining operation using existing resources, delivering, on average, 1.4-milion tonnes of ore for processing.

The processing plant will be located near the first two major deposits of graphite to be mined. The flowsheet comprises a flash and rougher flotation stage, followed by a primary cleaning circuit with a polishing mill and three stages of cleaner flotation. The intermediate concentrate is classified and then further upgraded in secondary cleaning circuits with stirred media mills followed by cleaner flotation.

The plant will comprise separate circuits, which will, ultimately, deliver an average of 75 000 t/y of graphite sold as concentrate, with the capacity to extend this after further drilling.

The life-of-mine is estimated at 13 years, but is likely to be extended as Blencowe has drilled only a small percentage of the total graphite available.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $317-million and an internal rate of return of 49%, with a payback of four years.

Capital Expenditure
Initial capital costs are estimated at $80-million, including a 15% contingency.

Planned Start/End Date
Not stated.

Latest Developments
Work will now begin on the prefeasibility study, which will include an upgraded Joint Ore Reserves Committee-compliant resource statement.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Blencowe Resources, tel +44 1624 681 250 or email info@blencoweresourcesplc.com.

Edited by Creamer Media Reporter

Comments

Projects

Copperwood project, US
Updated 4 hours ago By: Sheila Barradas

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.151 0.205s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: