https://www.miningweekly.com
blasting|Contractor|Crushing|Design|flotation|Gold|Mining|PROJECT|Resources|Storage|Waste|Water|Drilling|Waste
blasting|Contractor|Crushing|Design|flotation|Gold|Mining|PROJECT|Resources|Storage|Waste|Water|Drilling|Waste
blasting|contractor|crushing|design|flotation|gold|mining|project|resources|storage|waste-company|water|drilling|waste

Okvau gold project, Cambodia

31st January 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Okvau gold project.

Location
The project is located in the Mondulkiri province, in eastern Cambodia.

Project Owner/s
Renaissance Minerals, a wholly owned subsidiary of Emerald Resources.

Project Description
Okvau has an independent Joint Ore Reserves Committee-complaint indicated and inferred mineral resource estimate of 17.68-million tonnes grading 2.01 g/t gold, containing 1.14-million ounces at a 0.70 g/t gold cutoff.

The definitive feasibility study (DFS) is based entirely on probable reserves. Inferred resources, an estimated 7 000 oz within the final pit design, have not been included.

The DFS has confirmed the robust nature of the project, with an initial operating life-of-mine of more than seven years and production of about 106 000 oz/y of gold on average.

The deposit will be mined using conventional openpit mining methods from one pit at a relatively constant mining rate. Mining will be undertaken by drilling and blasting ore and waste, with loading and hauling being undertaken by a mining contractor.

The proposed processing plant has a throughput of two-million tonnes a year and will use a single-stage crushing circuit and semiautogenous milling circuit, sulphide flotation and regrind mill, followed by conventional cyanide leaching.

Tailings from the process plant will be disposed of in a dedicated tailings storage facility (TSF). The TSF will be located within a broad shallow valley to the south-east of the openpit, comprising a primary embankment to the south and a saddle embankment to the west. The waste-rock dump will be located to the north and north-west of the TSF and will be adjacent to the TSF embankment to enhance the structural stability of the TSF.

The proposed TSF development concept contains the currently envisaged life-of-mine tailings and provision for freeboard to contain process water and stormwater inputs. Assuming a tailings settled density of about 1.40 t/m3, tailings production of 14.3-million tonnes will require a storage requirement of about 10.5-million cubic metres. The TSF has been designed to accommodate 17.8-million cubic metres, including freeboard.

The project has an initial operating mine life of 7.2 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
A review of the DFS, at a higher gold price of $1 450/oz, has increased the projected net present value of the project from $217-million to $337-million and the internal rate of return from 48% to 69%, compared with the original DFS, which was based on a spot price of $1 250/oz.

Capital Expenditure
Total development costs have been estimated at $98-million.

Planned Start/End Date
Not stated.

Latest Developments
Emerald Resources will raise A$75-million through a share placement to fund development activities at its Okvau gold project.

The company will place an initial 762.1-million shares at a price of 4c each under its existing placement capacity to raise A$30.4-million, with a further 1.11-billion shares to be placed, subject to shareholder approval, to raise a further A$44.5-million.

A shareholder meeting is scheduled for March 13.

The offer price represents a 9.1% discount to Emerald’s closing price on January 20, and an 8.7% discount to the five-day volume weighted average share price, as well as a 6.2% discount to the ten-day volume weighted average share price.

Funds raised under the placement will allow for the continued development at Okvau while the company finalises a $60-million project finance facility.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Emerald Resources, tel +61 8 9286 6300, fax +61 8 9286 6333 or email info@emeraldresources.com.au.

Edited by Creamer Media Reporter

Comments

 

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 17 May 2024
17th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.139 0.191s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: