North Perth Basin mineral sands project, Australia – update

Image of mineral sands

Photo by ©Bloomberg

12th April 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
North Perth Basin mineral sands project.

Location
North Perth basin, Western Australia.

Project Owner/s
Image Resources.

Project Description
The Boonanarring and Atlas deposits form part of Image Resources’ North Perth Basin mineral sands project, which represents one of the highest-grade mineral sands resources under evaluation worldwide.

Boonanarring has a resource of 30.3-million tonnes at 6% heavy minerals, with a mineral assemblage that includes 20.4% zircon. The reserve is 10.7-million tonnes at 8.9% heavy minerals, with a mineral assemblage that includes 27.5% zircon.

The Boonanarring deposit will be mined first using conventional, dry and openpit mining techniques to extract the ore, and standard gravity separation in a wet concentration plant (WCP) to recover the contained heavy minerals into a heavy minerals concentrate (HMC) for sale. The HMC will be transported by road to a storage facility at Bunbury, where it will be loaded onto ships and transported in bulk to China.

Once mining at Boonanarring has been concluded, the WCP will be relocated to the Atlas deposit. Mining at Atlas will also be conducted using dry, opencut mining techniques. Over the life of the current ore reserves at Boonanarring, the HMC is expected to contain an estimated 610 000 t of ilmenite, 310 000 t of zircon, 25 000 t of rutile and 14 000 t of leucoxene.

The Atlas project is expected to start operation when Boonanarring is depleted, at which time key infrastructure, including the existing WCP, will be relocated from Boonanarring to Atlas.

At Atlas, production of about 210 000 t/y of HMC for 711 000 t/y is envisaged over the life-of-mine. The project has a resource of 18.1-million tonnes at 6% heavy minerals, with a mineral assemblage that includes 9.3% zircon, 46% ilmenite, 4% leucoxene and 6.5% rutile. Mineral reserves are estimated at 9.5-million tonnes at 8.1% heavy minerals, with a mineral assemblage that includes 10.6% zircon, 51% ilmenite, 4.5% leucoxene and 7.5% rutile.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value of A$235-million and an internal rate of return of 125%, with a payback of 13 months.

Capital Expenditure
Total developmental capital is estimated at A$51.7-million.

Planned Start/End Date
Not stated.

Latest Developments
Image has reported that the Atlas project is advancing to final Ministerial approval, following a three-week review period after the Environmental Protection Authority’s recommendation of the development plan for Atlas passed without any appeals.

The next steps for Atlas include Ministerial approval, approval of management plans and securing secondary project approvals to allow for the start of construction and mining.

Image has set a goal of starting construction early in the third quarter, mining and commissioning in the fourth quarter and HMC production in the first quarter of 2025.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Image Resources, tel +61 8 9485 2410, fax +61 8 94868312 or email info@imageres.com.au.

 

Edited by Creamer Media Reporter

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 10 May 2024
10th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.173 0.227s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: