https://www.miningweekly.com
Components|Construction|Engineering|Fabrication|Financial|Mining|PROJECT|Resources|Water|Products|Drilling
Components|Construction|Engineering|Fabrication|Financial|Mining|PROJECT|Resources|Water|Products|Drilling
components|construction|engineering|fabrication|financial|mining|project|resources|water|products|drilling

NiWest nickel/cobalt project, Australia – update

Location map of the NiWest nickel project

Photo by Alliance Nickel

27th October 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
NiWest nickel/cobalt project.

Location
Adjacent to Glencore’s Murrin Murrin operation, in the north-eastern goldfields of Western Australia.

Project Owner/s
Alliance Nickel, formerly GME Resources.

Project Description
An updated feasibility study has confirmed the robustness of a long-life operation producing high-purity nickel and cobalt sulphate products, to be delivered to lithium-ion battery raw material markets.

The mine and process schedule remain unchanged for the 2018 prefeasibility study (PFS) that proposes conventional openpit mining at a low strip ratio of 2:1.

Envisaged is a 27-year mining operation with a nameplate ore throughput of 2.4-million tonnes a year, resulting in total production of 456 000 t nickel (in nickel sulphate) and 31 400 t cobalt (in cobalt sulphate). Projected steady-state nickel and cobalt recoveries are estimated at 79% and 85% respectively.

Average production over the first 15 years is expected to be 19 200 t/y nickel and 1 400 t/y cobalt.

The processing route selected is heap leaching followed by neutralisation, impurity removal, direct solvent extraction and crystallisation to produce nickel and cobalt sulphate products.

Forecast operating and capital costs have been re-estimated through further prospective supplier interaction and general inflationary scaling.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The updated PFS presents three financial projections.

In Case 1, the project has a net present value, at an 8% discount rate, of A$1.88-billion and an internal rate of return of 21.6%, with a payback of 4.4 years.

In Case 2, the project has a net present value, at an 8% discount rate, of A$2.6-billion and an internal rate of return of 25.9%, with a payback of 3.7 years.

In Case 3, the project has a net present value, at an 8% discount rate, of A$3.31-billion and an internal rate of return of 29.7%, with a payback of 3.3 years.

Capital Expenditure
Preproduction capital expenditure has increased from A$966-million in the 2018 PFS to A$1.26-billion in the updated PFS.

Start/End Date
Construction is expected to take 24 months from the final investment decision, with the forecast heap pad and plant ramp-up phase taking about 20 months.

Latest Developments
The delivery of the definitive feasibility study (DFS) has been postponed to mid-2024.

“Unfortunately, the timing of completion for certain workstreams has impacted on the timing for completion of the overall DFS. Whilst . . . disappointing, the board considers it prudent [to take] . . . the necessary time to ensure all aspects of the project are advanced and completed diligently and comprehensively.

“Given the ongoing advanced progress of other project workstreams, completion of the DFS next year should not have a material impact on the overall project execution schedule,” MD and CEO Paul Kopejtka has said.

This postponement will allow for the completion of optimisation studies and water drilling programmes.

Cost optimisation engineering across major capital and operating cost estimates are under way, while international tender pricing continues for the acid plant, which is a material component of the project capital expenditure (capex).

Alliance Nickel’s engineering team has visited several overseas fabrication facilities to assess potential vendor capability. These meetings have been positive and competitive indicative pricing has been received, which would offset cost pressures across other components of the capex estimate.

Further, the company has completed drilling for water at its Mt Kilkenny tenements and other licensed areas. However, further water drilling programmes are required in other areas through access agreements with third parties. These programmes will run until the first quarter of 2024.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
GME Resources, tel +61 8 9336 3388, fax +61 8 9315 5475 or email enquiries@gmeresources.com.au.

Edited by Creamer Media Reporter

Comments

Showroom

ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.128 0.184s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: