Namoya heap-leach gold project, Democratic Republic of Congo
Name and Location
Namoya heap-leach gold project, Democratic Republic of Congo (DRC).
Client
Banro Corporation.
Project Description
The Namoya project is situated at the south-western end of the Twangiza-Namoya gold belt, in the Maniema province of the eastern DRC, and covers an area of 174 km2.
The preliminary assessment for the project proposes a two-million-ton-a-year heap-leaching processing facility and will produce about 131 000 oz/y of gold bullion, with an upfront, three-stage crushing system to produce 10 mm material, which will be agglomerated, transported and stacked on a permanent leach pad by a series of conveyors.
The proposed heap-leach operation could produce an average of 124 053 oz/y of gold, over a seven-year mine life.
The total installed power for the mine is estimated at 4 MW and will be provided by diesel generators.
Value
$148-million.
Duration
The bulk earthworks are expected to start in May 2012 and the plant is scheduled to be commissioned in March 2013.
Latest Developments
MDM Engineering has been awarded the engineering, procurement and construction management (EPCM) contract for the Namoya gold project.
Key Contracts and Suppliers
MDM Engineering (EPCM).
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Banro Corporation tel +1 416 366 2221 or email info@banro.com.
MDM Engineering, tel +27 11 993 4300, fax +27 11 886 9306 or email info@mdm-engineering.com.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation