Molo graphite project, Madagascar – update

Image of a box of graphite

3rd December 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Molo graphite project.

Location
Tulear region, south-western Madagascar.

Project Owner/s
Canadian battery materials development company NextSource Materials.

Project Description
The Molo project is a full feasibility study-stage project and ranks as one of the biggest-known and highest-quality flake graphite deposits in the world; it is the only project with SuperFlake graphite.

NextSource will use an all-modular build approach to build the mine.

Initial production is expected to be 17 000 t/y over the first two years of production, followed by mine expansion in Year 3.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
A $29.5-million strategic investment by Vision Blue is expected to fully fund the construction of the project.

Planned Start/End Date
Mine commissioning is targeted for April 2022.

Latest Developments
The construction of the Molo graphite project is on schedule and within budget.

The company’s engineering, procurement and construction management (EPCM) contractor, Erudite Strategies, reports that the attrition and ball mills, crushers, flotation columns, screeners, feeders, mixing tanks, bagging and drying systems have been fabricated and are ready for assembly.

The equipment comprises the major components of the Molo mine processing plant and will shortly be received by NextSource’s engineering, procurement and construction (EPC) firm to start assembling the modules.

The EPC firm specialises in the design, engineering, construction and assembly of fully modular processing plants, which, according to NextSource, is why the Molo mine can have a very low mine capital cost, compared with that of competitors, and can reach the commissioning stage in 12 months from the start of construction.

NextSource personnel have been mobilised to Madagascar to start preparations for site works.

Plant equipment is on track to be delivered to site in the first quarter of 2022, with plant equipment module installation at site on schedule to start in the first half of 2022.

NextSource has said it does not require any more funding to reach commissioning, which is on schedule for the second quarter of 2022, after receiving $29.5-million from its strategic investor Vision Blue Resources in May.

Key Contracts, Suppliers and Consultants
Erudite Strategies (EPCM contractor).

Contact Details for Project Information
NextSource Materials, tel +1416364 4911 or executive VP corporate development Brent Nykoliation, email brent@nextsourcematerials.com.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 17 May 2024
17th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.179 0.24s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: