Marlin ships record gold as La Trinidad output ramps up
VANCOUVER (miningweekly.com) – Junior miner Marlin Gold has shipped a record 10 121 oz of gold from its cornerstone La Trinidad mine, in Mexico, in January.
The Vancouver-based miner attributed the improved performance to consistently accessing the higher-grade HS Zone since September, allowing it to stack more ore on the heap leach pad.
Marlin also expects total costs per ounce shipped to be below $290 for January, but noted that costs would increase to more than the previous $2.25-million to $2.5-million monthly cost estimate, as the company accelerates mining to reach the southern part of the high-grade HS Zone.
All-in mining costs, including drilling, loading, blasting, hauling, diesel and explosives are about $1.70/t for January.
Since September, Marlin has stacked 66 923 oz of gold, with 7 447 oz stacked in January alone. The tonnes stacked in January had an average grade of about 1.87 g/t.
Further, Marlin has built up about 485 000 t of ore in stockpile grading about 1.37 g/t.
Management expects to process grades similar to the average stockpile grade as it accelerates mining to reach the southern part of the high-grade HS Zone by the third quarter of this year.
The recoveries of gold from the leach pad are approaching steady state and averaged 231 oz/d in January, the company reported.
“With the processing of our current stockpile, and accelerated southern HS Zone mine plan, management now expects consistent operating cash flow for at least the next two full years, confirming what was estimated by the second amended National Instrument 43-101 technical report dated February 1, 2013, and prepared by SRK Consulting,” the company said in a statement.
Marlin’s TSX-V-listed stock closed in the red on Monday, losing 5.71% to C$0.66 apiece.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation