https://www.miningweekly.com
Cleaning|Construction|Copper|Design|Engineering|Explosives|flotation|Gold|Manufacturing|Mining|Platinum|PROJECT|Resources|Services|Testing|Waste|Equipment|Manufacturing |Environmental|Waste
Cleaning|Construction|Copper|Design|Engineering|Explosives|flotation|Gold|Manufacturing|Mining|Platinum|PROJECT|Resources|Services|Testing|Waste|Equipment|Manufacturing |Environmental|Waste
cleaning|construction|copper|design|engineering|explosives|flotation|gold|manufacturing|mining|platinum|project|resources|services|testing|waste-company|equipment|manufacturing-industry-term|environmental|waste

Marathon palladium and copper project, Canada

7th May 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Marathon palladium and copper project.

Location
Marathon, in north-western Ontario, Canada.

Project Owner/s
The project is a joint venture (JV) between Generation Mining (Gen Mining), which owns an 80% interest in the project, with the remaining interest owned by Sibanye-Stillwater.

Project Description
A feasibility study completed on Marathon in March 2021 has confirmed it is a substantial mining project that is expected to provide a very robust return on investment.

Mineral reserves are estimated at 117.7-million tonnes grading 0.62 g/t 0.21% copper, 0.07 g/t gold and 0.2 g/t platinum. The project has a mineral and indicated resources of 244.87-million tonnes grading 0.53 g/t palladium, 0.20% copper, 0.07 g/t gold and 0.18 g/t platinum. Inferred resources are estimated at 33.85-million tonnes grading 0.40 g/t palladium, 0.22% copper, 0.05 g/t gold and 0.1 g/t platinum.

The proposed mine will use conventional openpit, truck-and-shovel operating methods. Three pits will be mined over the 13-year mine life, with an additional two years of preproduction mining to be undertaken where waste material will be mined for construction and ore stockpiled ahead of processing plant commissioning.

The mining equipment fleet will be owner-operated and will include the outsourcing of certain support activities such as explosives manufacturing and blasting.

Mining production at peak capacity is estimated at 40-million tonnes a year, or 110 000 t/d. Total material moved over the life of the operation is 447-million tonnes, with 118-million tonnes of ore mined.

The openpit operation includes a waste-rock dump east of the openpit, as well as an ore stockpile, with a peak capacity of about 12-million tonnes, to the west of the pits, close to the crusher location.

The project process design is based on the optimised flowsheet and is designed to operate at 9.2-million tonnes a year, or 25 200t/d, and will produce a copper/palladium concentrate for marketing.

The process plant flowsheet includes a conventional comminution circuit comprising a semi-autogenous grinding mill and pebble crusher followed by a ball mill. The flotation portion of the process plant includes rougher flotation, concentrate regrind and three stages of cleaning.

After the initial construction phase, the palladium-scavenger or platinum group metals (PGM) scavenger circuit will be installed. Included in construction is cyclone classification of rougher tailings to reject the fine fraction and submit coarser fractions to additional regrinding and PGM scavenger flotation. The PGM-scavenger circuit will add incremental recovery improvement to achieve the recoveries established in the 2020 metallurgical testing programmes.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
In the base case, the project has a pretax net present value, at a 6% discount rate, of $1.64-billion and an internal rate of return of 38.6%, with a payback of 1.9 years.

Capital Expenditure
The project is estimated at $665-million.

Planned Start/End Date
The initial capital cost considers a site-based construction timeframe of about 18 months, followed by commissioning and ramp-up to commercial production over an estimated nine months. The company expects to begin construction in 2022 subject to permitting approvals and financing arrangements.

Latest Developments
Sibanye-Stillwater and the JV management committee have not yet reviewed nor approved the feasibility study. Gen Mining plans to advance the environmental approval process, detailed engineering and financing for the mine during the remainder of 2021.

Key Contracts, Suppliers and Consultants
G Mining Services, with contributions from Ausenco Engineering Canada, Haggarty Technical Services, Knight Piésold, WESC Inc. and P&E Mining Consultants (feasibility study).

Contact Details for Project Information
Gen Mining president and CEO Jamie Levy, tel +1416567 2440 or email jlevy@genmining.com.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.108 0.162s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: