https://www.miningweekly.com

Botswana project receives modular building solutions

TIGHT DELIVERY SCHEDULE
Speedspace delivered 4 256 m2 of preassembled buildings to house contractors at BCL’s smelter plant for its shutdown programme

TIGHT DELIVERY SCHEDULE Speedspace delivered 4 256 m2 of preassembled buildings to house contractors at BCL’s smelter plant for its shutdown programme

28th August 2015

By: David Oliveira

Creamer Media Staff Writer

  

Font size: - +

Prefabricated building supplier Speedspace delivered 4 256 m2 of mobile preassembled building solutions to Botswana government-owned nickel and copper producer BCL last month.

Company MD Hennie Wiggett notes that the 135 units, including housing, ablution facilities, offices, security units and steel storage containers, are being used for contractors working on BCL’s smelter plant shutdown programme to upgrade and refurbish the smelter in Selebi-Phikwe, Botswana, which started in July. Production at the smelter is scheduled to resume next month.

The mobile units were constructed using 40 mm polyurethane core panels with external chromadek cladding mounted onto a steel chassis.

Wiggett points out that the preassembled units are equipped with electrical fittings, air conditioning and plumbing. “Once the units arrived on site, all that was needed . . . was to connect them to the mine’s electrical, waste and water service.”

He explains that the units are put in position using trucks and trailers. The units are then lifted with a crane, the trailer is removed, and the units are lowered onto the supporting bases or jacks.

Wiggett states that the most difficult aspect of the project was meeting the tight one-month delivery deadline. He notes that the contract was awarded to Speedspace Botswana; however, to meet the deadline, the company’s South African office was commissioned to deliver about 70% of the order, as it has the capacity to execute large orders.

He adds that the size of the order resulted in a significant logistics challenge, with between 12 and 16 trucks from the company’s transport division, Speedspace Transport, having been used to deliver two to three loads a week from South Africa to Botswana. Wiggett highlights that the turnaround time for delivery of each load was between two and two-and-a-half days.

Meanwhile, Speedspace completed a proof-of-concept project in June at iron-ore major Kumba Iron Ore’s Sishen mine, in the Northern Cape, where the company installed wind-bracing technology on three of the mine’s modular buildings.

Wiggett explains that the iron-ore mine has been subjected to unusually high speed winds in recent years, which pushed some of the buildings off their jacks, creating a significant safety risk.

Speedspace was required to develop a solution to prevent the buildings from toppling over. Wiggett notes that the company used concrete railway sleepers, which are in abundance at Sishen, with stainless steel cable to anchor the buildings.

The railway sleepers were placed underneath the units and tied to the building chassis at an angle. Speedspace’s appointed engineering team and Sishen’s engineers completed a number of load tests to determine the downward weight-bearing factor of the solution. The solution successfully proved its efficacy in resisting the wind forces and has resulted in the mine specifying this solution for all future installations.

“The process was interesting because of the way in which the engineers we appointed and the mine engineers worked together to develop a solution that is workable and safe, and requires very little site work to complete,” Wiggett concludes.

Edited by Leandi Kolver
Creamer Media Deputy Editor

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.164 0.201s - 115pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: