Lupaka starts shipping Invicta ore for toll mill testing
TORONTO (miningweekly.com) – TSX-V- and BVL-listed Lupaka Gold has started shipping a 900 t ore sample from its Invicta gold mine site for an initial toll mill test campaign at a toll mill near La Oroya, in central Peru.
The processing campaign would test and demonstrate grinding and recovery kinetics, chemical consumption, treatment cost and final concentrate grade performance.
The campaign at the San Juan Evangelista plant was expected to run until late in September and the results would be available soon after. The plant would generate copper/gold, lead/silver and zinc concentrate products.
"The project is advancing as planned toward the start of operations later this year. The Invicta project is one of the few near-term production projects that we see in the gold sector today.
“Given our progress over the last year, excellent grades, in-place operating permits, infrastructure and supportive community relations, we remain committed to advancing the project,” Lupaka president and CEO Eric Edwards stated.
Consulting engineering firm Certimin would supervise the bulk test to collect enough processing performance data to guide the design and potential construction of the company’s own dedicated process plant.
The Invicta gold project contained a polymetallic resource primarily comprised of gold with extra copper and, to a lesser degree, lead, silver and zinc.
Lupaka aimed at starting production at an initial rate of 100 t/d this year, scaling up to 350 t/d, subject to available financing. The mining operations would at first target some of the highest-grade gold and copper mineralisation within the project's Atenea vein.
The company was also looking at potentially buying a process plant or site closer to the Invicta mine to provide for the most efficient growth and expansion of the project.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation