https://www.miningweekly.com
Building|Civils|Construction|Design|Energy|Engineering|Fabrication|Logistics|Manufacturing|Mining|Power|PROJECT|Resources|Road|Screening|Screens|Steel|transport|Contracting|Equipment|Manufacturing |Products
Building|Civils|Construction|Design|Energy|Engineering|Fabrication|Logistics|Manufacturing|Mining|Power|PROJECT|Resources|Road|Screening|Screens|Steel|transport|Contracting|Equipment|Manufacturing |Products
building|civils|construction|design|energy|engineering|fabrication|logistics|manufacturing|mining|power|project|resources|road|screening|screens|steel|transport|contracting|equipment|manufacturing-industry-term|products

Lindi Jumbo graphite project, Tanzania – update

Image of pieces of graphite from the Lindi Jumbo project

29th October 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Lindi Jumbo graphite project.

Location
South-east Tanzania.

Project Owner/s
Walkabout Resources.

Project Description
The Lindi Jumbo project has mineral ore reserves of 5.15-million tonnes grading 17.9% total graphitic carbon for 987 000 t of con­tained graphite.

The mine life has increased from 20 years in the 2017 definitive feasibility study (DFS) to 24 years in the enhanced DFS to produce 40 000 t/y of graphite.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The pretax net present value has increased from $302-million, at a 10% discount rate, in the 2017 DFS, to $335-million in the enhanced DFS. The project’s pretax internal rate of return is estimated at 142% in the enhanced DFS, from 108% in the 2017 DFS. The payback period is less than two years.

Capital Expenditure
Preproduction capital costs have decreased from $29.7-million in the 2017 DFS to $27.8-million in the enhanced DFS.

Planned Start/End Date
The construction schedule has not been modified in the enhanced DFS, as commissioning can be achieved 9 to 12 months after project-start funding has been received.

Latest Developments
Walkabout Resources has said its mine construction schedule at the Lindi Jumbo graphite mine is on track.

An engineering, procurement and construction (EPC) contract for the Lindi Jumbo graphite process plant has been concluded with Yantai Jinpeng Mining and Machinery in China.

This follows the mobilisation payment made to Jinpeng in September to activate the contract.

The execution of the second material contract is part of the conditions precedent for drawdown of the $20-million debt facility with CRDB Bank in Tanzania.

The project capital expenditure is substantially derisked with this contract being for a fixed price. Together with the previously announced earthmoving and civils contract with TNR, more than two-thirds of the project is now contracted.

The EPC contract sum, including the plant enhancement scope change, is $11.9-million.

Of this, $500 000 has already been paid as part of the early start programme and a further $1.6-million paid on mobilisation. The contract allows for additional separable portions for power, mobile equipment and shipping.

Walkabout will source the mobile equipment from Jinpeng for $600 000. It includes a telehandler, front-end loaders and mobile crane. Mine power is subject to a separate contracting process with alternative vendors.

The EPC contract costs have been revised to current market prices predominantly for steel and labour.

An estimated escalation of 150% in shipping costs to the original budget has arisen owing to the global Covid-19 pandemic-influenced shortage of shipping containers. The resulting increase in fixed cost from the original budget is currently not seen as material and negotiations are under way in the various remaining areas of the project to likely offset these increases.

Meanwhile, Walkabout has exercised its option to apply an upgraded design to the back-end of the plant that deals with the screening and bagging of the graphite concentrate. This change of scope includes the redesign of the final processing building, which is larger, to include enhanced screens and supporting equipment and automated bagging units.

These changes will not only improve plant precision for sorting final products but also provide options consistent with its growth intentions, the company notes.

The incremental cost of adding these scope changes to the EPC contract is about $1.5-million.

Since the mobilisation payment made to Jinpeng in September, manufacturing and procurement progress at Jinpeng has run according to schedule.

Axis Group International, acting as the Lindi Jumbo representative at Jinpeng, has been undertaking quality management checks on the procured construction materials and completed works. The first shipment batch is planned to be dispatched by mid-November.

To date, the power rationing in China, aimed predominantly at high energy consuming industries, has not affected Jinpeng and there has thus been no adverse effect on their  procurement and fabrication schedule.

The company is finalising the appointment of a local Tanzanian logistics company to receive the batches at the port, manage customs clearance and the road transport to site. This company will work closely with Jinpeng and the Axis Group International to ensure that the potential for clearance and transport delays is minimised.

Site bulk earthworks in Tanzania are progressing to schedule and within budget.

The excavation and terracing of the processing plant area is nearing completion.

Key Contracts, Suppliers and Consultants
TNR (bulk earthworks civil engineering works contract) and Yantai Jinpeng Mining Machinery (EPC) and Axis Group International (EPC oversight).

Contact Details for Project Information
Walkabout Resources, tel +61 8 6298 7500 or email admin@wkt.com.au.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.135 0.191s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: