Kibo receives final commercial bids for Mbeya project

1st November 2016

By: Anine Kilian

Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – The final commercial bids for Kibo Mining’s Mbeya coal-to-power project’s (MCPP’s) engineering, procurement and construction (EPC) and original-equipment manufacturer (OEM) contracts were received from Sepco III and General Electric (GE) on October 31, the Tanzania-focused company announced Tuesday.

The signing of the final EPC and OEM contracts is currently scheduled for the end of December. Kibo has also submitted its mining right application for Mbeya.

Tractebel Engineering (TE) will now subject both bids to a stringent benchmark, previously developed by TE, to determine whether the bids comply with international best standards, practice and price. The bids also need to meet specific conditions that were stated in the respective bid specifications.

The benchmarking process will be completed over the next three weeks, whereafter the company and its technical, financial and legal advisers will engage Sepco III and GE in a final round of negotiations by the beginning of December.

"We have achieved significant progress at the MCPP in 2016 and, by the end of the year, we will have met all of its ambitious 2016 development targets, albeit that not all were met within the original target dates, in spite of limited financial resources as well as delays caused by policy reviews and changes in Tanzania,” noted CEO Louis Coetzee.

MCPP is now independently recognised as a robust, well-advanced project. 

“It is disappointing that we will not be as far advanced with financial close as previously anticipated, owing to the fact that we cannot proceed with the finalisation of the power purchase agreement, until such time as the Tanzanian government has completed its policy review process,” he said.

Coetzee added that the company is in constant discussion with government on this matter and has received continued cooperation and reassurance that it will be able to make up for the time lost during the policy review process.

“Owing to this delay, we will have to reschedule certain activities to ensure that the MCPP development timeline is not compromised,” he said.

Edited by Samantha Herbst
Creamer Media Deputy Editor

Comments

Latest News

ASM CEO and MD Rowena Smith
ASM secures another financing letter of intent from Canadian agency
Updated 7 hours ago By: Marleny Arnoldi

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
Updated 7 hours ago
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.873 0.907s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: