Kibo completes first phase of mining feasibility study

15th October 2015

By: Megan van Wyngaardt

Creamer Media Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – The first phase of a definitive mining feasibility study (DMFS) at dual-listed Kibo Mining’s Mbeya coal-to-power project (MCPP), in Tanzania, has been completed, bringing the project closer to the final stage of its broader mining feasibility study. 

The first phase, carried out in collaboration with Kibo’s advisers Minxcon Projects, mainly entailed a geotechnical drilling programme on the Mbeya coal mine site, with 90% of the work scheduled consisting of the 820 m diamond core drill programme.

The geotechnical drill programme represented a mission-critical component of the DMFS and was required to confirm the ground conditions in and around the final pit position, which, in turn, determined the final slope angles in the pit design. The final slope angles were a prerequisite for final and detailed mine design.
 
The drill programme comprised eight holes, accurately angled and directed at specific strategic positions to penetrate the pit hanging wall at depths varying from 95 m to 120 m. Geotechnical samples were collected from the recovered core and submitted for laboratory analysis and these results would form the basis of the geotechnical input parameters for the final mine design during the DMFS. Visual assessment of the core also reconfirmed all previous geotechnical findings to date.
 
To accelerate development, Kibo designed the geotechnical drill programme to double up as an extensive metallurgical sampling programme. The metallurgical analysis to be conducted from the sampling programme, would verify specific coal properties that were required for detailed design requirements of the MCPP power station component.
 
Combining the two activities also brought about a significant saving on the MCPP feasibility study budget, as a separate drill programme for the purposes of metallurgical testing would now not be required. It also provided a significant amount of new data that would enable a restatement of the Mbeya coal resource, during Phase 2 of the DMFS.
 
The programme was executed and completed within scope, schedule and budget. Laboratory results are expected within eight weeks.

“The MCPP, as an integrated project, is persistently growing in stature. This is best reflected in the continued progress we are making towards concluding critical commercial arrangements on the MCPP, to ensure optimal value creation and realisation on the company's flagship asset. These efforts are, in turn, strongly supported by the ongoing feasibility work that is continuing in parallel and at pace,” Kibo Mining CEO Louis Coetzee said.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 
SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.129 0.166s - 106pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: