https://www.miningweekly.com
Building|Construction|Design|Energy|Engineering|Fabrication|Financial|generation|Infrastructure|Mining|Power|PROJECT|Resources|Environmental|Infrastructure
Building|Construction|Design|Energy|Engineering|Fabrication|Financial|generation|Infrastructure|Mining|Power|PROJECT|Resources|Environmental|Infrastructure
building|construction|design|energy|engineering|fabrication|financial|generation|infrastructure|mining|power|project|resources|environmental|infrastructure

Kathleen Valley lithium/tantalum project, Australia – update

Imahe of lithium product

Photo by Liontown Resources

13th October 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project                                    
Kathleen Valley lithium/tantalum project.

Location
North-east Goldfields of Western Australia.

Project Owner/s
Lithium developer Liontown Resources.

Project Description
A definitive feasibility study (DFS) has confirmed the potential to develop a state-of-the-art, second-generation lithium/tantalum mining and processing operation.

The DFS optimises the mine schedule, process plant design and forecast sales pricing to enhance the technical and financial viability of a standalone, long-life, four-million-tonne-a-year operation.

The project has an ore reserve of 68.5-million tonnes grading 1.34% lithium oxide and 120 parts per million tantalum pentoxide, underpinning an initial estimated 23-year mine life, based on the updated mining schedule.

Building on the October 2020 prefeasibility study (PFS), the DFS base production has been increased from two-million tonnes a year to 2.5-million tonnes a year, producing about 500 000 t/y of spodumene concentrate, with a four-million-tonne-a-year expansion planned in Year 6 to deliver about 700 000 t/y spodumene concentrate.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a real 8% discount rate, of A$4.2-billion and an internal rate of return of 57%, with a payback of 2.3 years.

Capital Expenditure
Capital costs for the project are now estimated at A$951-million, up from the previous estimate of A$895-million.

Planned Start/End Date
First production is expected to start in the first half of 2024.

Latest Developments
Unlisted Hancock Prospecting has achieved its objective of a 19.9% ownership in lithium developer Liontown Resources, as that company extends its due diligence talks with critical minerals major Albemarle.

Hancock is now looking forward to having a "prominent influence on Liontown's future” as the company’s now-biggest shareholder.

Hancock previously expressed its concerns about Liontown’s ability to bring the Kathleen Valley project to fruition, after Liontown warned that capital costs for the project were now estimated at A$951-million, up from the previous estimate of A$895-million. Liontown also shelved plans for a direct shipping ore operation at Kathleen Valley on the back of falling lithium prices, a move which has drawn criticism from Hancock.

It has been widely speculated that Hancock’s increasing stake in Liontown will give the company the leverage to block a takeover offer from critical minerals major Albemarle.

Albemarle is in the middle of a due diligence on Liontown after announcing a A$6.6-billion bid for Liontown, tentatively offering A$3 a share for the ordinary outstanding shares in the company.

Albemarle has been granted a short extension on its due diligence process, following a request from the company. The exclusive due diligence period has been extended by seven days, on the same terms.

Key Contracts, Suppliers and Consultants
ZOOID (environmental, social and governance); Optiro (geology and mineral resources estimate); Snowden Mining Industry Consultants (mine optimisation, planning, design and scheduling); ALS Metallurgy (process testwork); Lycopodium Minerals (process and infrastructure design, capital and operating expenditure); Knight Piésold (tailings and hydrogeology); MBS Environmental (environmental studies); Peter O’Bryan and Associates (geomechanical engineering); Metso-Outotec (design, fabrication and delivery of a semiautogenous grinding mill); Lycopodium Minerals (engineering, procurement and construction management); and Zenith Energy (hybrid power station – design, build, own, operate and maintain).

Contact Details for Project Information
Liontown Resources, tel +6 8 6186 4600 or email info@ltresources.com.au.

Edited by Creamer Media Reporter

Comments

Latest Multimedia

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.249 0.3s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: