Kathleen Valley lithium/tantalum project, Australia

19th July 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kathleen Valley lithium/tantalum project.

Location
The project is located in Western Australia’s north-eastern goldfields.

Client
Liontown Resources.

Project Description
A scoping study has demonstrated the potential of the Kathleen Valley project to support a viable standalone lithium mining and processing operation.

The scoping study outlines a base case two-million-tonne-a-year development with the potential to produce about 360 000 t/y of spodumene concentrate over an initial eight- to nine-year mine life.

The project has a life-of-mine production target of 15.7-million tonnes of ore.

The Kathleen Valley Project process plant consists of a mineral processing concentrator with associated services and ancillaries. It includes:
• three-stage crushing;
• two-stage dense-medium separation (DMS) to produce a primary concentrate, a coarse tail and a middling product for further treatment;
• ball milling of the middling product;
• three-stage flotation to produce a fine;
• concentrate and fine tails;
• rod milling and gravity/magnetic separation to produce a tantalum concentrate;
• thickening and filtration of the concentrate;
• coarse and tails disposal; and
• reagents and services.

The coarse tail from the DMS plant will be loaded onto trucks and placed in the waste stockpile area. The fine tail from the flotation plant will be thickened and then pumped to a separate storage facility.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of between A$316-million and A$526-million, with a base case of A$421-million and an internal rate of return of 38%. Payback is estimated at less than three years.

Value
The project is estimated at A$232.2-million.

Duration
It is currently estimated that construction could start in 2021, with first production in 2022.

Latest Developments
The mineral resource estimate for the Kathleen Valley lithium/tantalum project has increased by 353%, on the back of new drilling results.

The Kathleen Valley measured, indicated and inferred resource is now estimated at 74.9-million tonnes grading 1.3% lithium oxide and 140 parts per million of tantalum pentoxide, containing about 0.97-million tonnes of lithium oxide and 2.5-million tonnes of lithium carbonate equivalent.

Liontown MD David Richards has said that the deposit is high grade, with a significant tantalum component, and outcropping mineralisation meaning it will be largely amenable to openpit mining.

“In addition, it is located on granted mining leases close to established, modern, high-quality infrastructure. The other encouraging feature of the project is that, based on the initial metallurgical results and ongoing testwork, the lithium mineralisation, which is spodumene-related, is likely to be conducive to conventional processing.”

A prefeasibility study for Kathleen Valley is under way and due for release in the fourth quarter.

Key Contracts and Suppliers
Optiro (geology and resources); Orelogy Consulting (optimisation and mining); Nagrom (process testwork); Lycopodium Minerals (process and infrastructure design, capital and operating expenditures); Knight Piésold (tailings management facilities); AQ2 (hydrology and hydrogeology); and MBS and Botania (environmental studies).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Liontown Resources, tel +61 8 9322 7431 or email info@ltresources.com.au.

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Showroom

Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.2 0.253s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: