Katanga on track to commission WOL project in Q4

4th May 2017

By: Megan van Wyngaardt

Creamer Media Contributing Editor Online

     

Font size: - +

JOHANNESBURG (miningweekly.com) – TSX-listed Katanga Mining will continue to focus on waste mining ahead of the commissioning of its whole ore leach (WOL) project, in the Democratic Republic of Congo.

Katanga mined 5.39-million tonnes during the quarter ended March 31, a 250% increase on that mined in the fourth quarter of 2016 and 560% higher year-on-year.

The company attributed the uptick to increased waste mining activities in view of the commissioning of the WOL project, which is expected to start in the fourth quarter.

The company in September 2015 suspended the processing of copper and cobalt to allow for the construction of the WOL project, which was still ongoing.

The miner reported that significant progress had been made on the structural, mechanical, platework and piping activities on the acid tanks, preleach and leach trains, with related capital expenditure amounting to $31.1-million.

Concurrent with the construction of the WOL project plant and infrastructure, the current life-of-mine plan continues to be optimised to ensure the appropriate blend will be supplied to the WOL project process when complete, to increase copper and cobalt recovery and to reduce operating cost per unit.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 
Essentra Components
Essentra Components

We are responsible manufacturers of essential components. Manufacturing 80 million parts a week, we have over 1 billion parts in stock.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Northern Cape copper, South African PGMs make headlines
Northern Cape copper, South African PGMs make headlines
10th July 2026 By: Creamer Media Reporter
A video round up of this week’s magazine, highlighting our cover story, features and Business Leader.
Magazine round up | 10 July 2026
10th July 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.055 0.079s - 134pq - 2rq
Subscribe Now