https://www.miningweekly.com
Africa|Botswana|Construction|Energy|Engineering|Excavators|Mining|PROJECT|Safety|Service|Surface|Training|Trucks|Underground|Water|Equipment|Shaft Sinking|Operations
Africa|Botswana|Construction|Energy|Engineering|Excavators|Mining|PROJECT|Safety|Service|Surface|Training|Trucks|Underground|Water|Equipment|Shaft Sinking|Operations
africa|botswana|construction|energy|engineering|Excavators|mining|project|safety|service|surface|training|trucks|underground|water|equipment|shaft-sinking|operations

Karowe underground project, Botswana – update

Aerial view of Karowe mine

24th February 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Karowe underground project.

Location
Botswana.

Project Owner/s
Lucara Diamond Corp.

Project Description
The Karowe mine is an existing conventional drill-and-blast openpit operation, with diesel excavators and trucks providing an average of 2.6-million tonnes a year of kimberlite feed for the mill. The openpit mine operation is expected to terminate in mid-2026, ending at an elevation of about 700 m above sea level.

The project is expected to extend the mine life to at least 2040, with underground carat production coming predominately from the highest-value EM/PK(S) unit.

Longhole shrinkage underground bulk mining has been selected to provide early access to higher-value ore and allow for a short payback period.

The underground project is designed to access the South Lobe kimberlite resource below the current planned bottom of the openpit, which is expected to be at about 700 m above sea level, to a depth of 310 m above sea level.
 
Access to the South Lobe underground will be through two vertical shafts.

A 767-m-deep production shaft, 8.5 m in diameter, driven from surface, will be equipped with two 21 t skips for production hoisting and a service cage for man-and-material movement through the mine. This shaft will also serve as the main fresh-air intake to the mine.

A second shaft, 6 m in diameter, driven 733 m deep from surface, will form the main ventilation exhaust pathway.

All underground mined kimberlite will be processed at the existing Karowe processing plant over a 13- to 15-year period following the cessation of the current openpit operations, which is expected to occur in 2026.

Life-of-mine production (remaining openpit and underground) is estimated at 7.4-million carats.

The underground expansion is expected to extend Karowe’s mine life by 13 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 5% discount rate, of $750-million, with a payback of about three years, for the combined openpit and underground mine.

Capital Expenditure
Lucara has updated the estimated capital cost, reporting an increase from $534-million to $547-million to reflect expected pricing changes following the execution of the main sink contract. The underground expansion is expected to extend Karowe’s mine life by 13 years.

Planned Start/End Date
The company will complete shaft sinking in 2024 and the ramp-up is scheduled for the first quarter of 2026, with full production from the underground mine expected in the second half of that year.

Latest Developments
Work on the Karowe underground project has made significant strides in the past year, achieving several important milestones.

All presinking activities have been completed on schedule and budget, a main shaft sinking contract has been executed and main shaft sinking activities are continuing to ramp up.

However, equipment and operational challenges are negatively impacting on planned cycle times. Cycle time is the period it takes to complete a series of activities within the sinking process to achieve the next planned vertical advance.

Lucara states that it has made equipment and personnel changes, as well as shift and rotation schedule optimisations along with the roll-out of a behavioural-based safety training programme to resolve these issues.

“The impact of delays and a slower-than-anticipated ramp-up in shaft sinking cycle times, together with experience gained from our first grouting programme will be incorporated into a refreshed schedule and budget which is expected to be completed in the second quarter of 2023,” president and CEO Eira Thomas has said.

Lucara completed the first phase of grouting in the production shaft between December and February, confirming the planned approach and methodology to keep water inflows from the stand stones at bay.

During 2022, Lucara invested $106-million in the Karowe project, with a total investment to date of $226.1-million. The company is working on a capital cost estimate of $547-million for the project.

Key Contracts, Suppliers and Consultants
UMS Botswana (presink construction contract); UMS South Africa (shaft sinking equipment procurement); UMS subsidiary METS International (shaft engineering contract); and JDS Energy & Mining (engineering, procurement and construction management) for the execution of the Karowe underground project.  

Contact Details for Project Information
Lucara Diamond Corp, investor and public relations, tel +1 604 674 0272 or email info@lucaradiamond.com.

Edited by Creamer Media Reporter

Comments

Showroom

Universal Storage Systems (SA)
Universal Storage Systems (SA)

South African leader in Steel -Racking, -Shelving, and -Mezzanine flooring. Universal has innovated an approach which encompasses conceptualising,...

VISIT SHOWROOM 
AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.102 0.152s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: