https://www.miningweekly.com
Botswana|Construction|Design|Engineering|Excavators|Flow|Mining|PROJECT|Resources|Trucks|Underground|Flow|Operations
Botswana|Construction|Design|Engineering|Excavators|Flow|Mining|PROJECT|Resources|Trucks|Underground|Flow|Operations
botswana|construction|design|engineering|Excavators|flow-company|mining|project|resources|trucks|underground|flow-industry-term|operations

Karowe diamond mine underground expansion, Botswana – update

8th January 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Karowe diamond mine underground expansion.

Location
Botswana.

Project Owner/s
Lucara Diamond Corp.

Project Description
The Karowe mine is an existing conventional drill-and-blast openpit operation, with diesel excavators and trucks providing an average of 2.6-million tonnes a year of kimberlite feed for the mill. The openpit mine operation is expected to terminate in mid-2025, ending at an elevation of about 700 m above sea level.

The combined openpit and underground indicated resource is estimated at 54.27-million tonnes at 15.3 carats per hundred tonnes for a contained diamond resource of 8.3-million carats, excluding stockpiles.

The feasibility on the proposed project has focused on the substantial resources remaining below the economic extents of the openpit.

Longhole shrinkage underground bulk mining has been selected to provide early access to higher-value ore and allow for a short payback period.

The underground project is designed to access the South lobe kimberlite resource below the current planned bottom of the openpit, which is expected to be at about 700 m above sea level, to a depth of 310 m above sea level.

Access to the South lobe underground will be through two vertical shafts – production and ventilation – of about 765 m and 715 m respectively.

All underground mined kimberlite will be processed at the existing Karowe processing plant over a 13- to 15-year period, following the cessation of the current openpit operations, which is expected to occur in 2025.

Life-of-mine production (remaining openpit and underground) is estimated at 7.8-million carats.

The underground expansion is expected to extend Karowe’s mine life by 15 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 5% discount rate, of $718-million, with a payback of 2.8 years, for the combined openpit and underground mine.

Capital Expenditure
Preproduction capital costs for the underground project are estimated at $513.7-million.

Planned Start/End Date
Based on construction starting in mid-2020, ore from underground mining will seamlessly integrate into current operations providing mill feed in 2023, with a ramp-up to 2.7-million tonnes a year to the processing plant by 2026.

Latest Developments
The mining licence renewal application for Lucara Diamond Corp and Lucara Botswana’s Karowe mine, in Botswana, has been approved, and is effective from January 4 for 25 years.

This secures Lucara’s mining rights until 2046 and marks a critical step in the formal sanction of the Karowe underground expansion project.

Lucara president and CEO Eira Thomas has said that the receipt of the mining licence renewal and extension is an important milestone for the Karowe underground expansion project, and “paves the way for the completion of a supplemental debt financing and full project sanction” later this year.

The Karowe underground expansion project, which continued to advance in 2020 under a revised $22-million budget in response to the Covid-19 pandemic, focused on time critical path items, detailed engineering and design, and limited earthworks and geotechnical studies.

Lucara continues to explore debt financing options for the underground expansion for those amounts which are expected to exceed the company's cash flow from operations during the construction period.

Financing is expected to be in place by the second half of 2021.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Lucara Diamond Corp investor and public relations, tel +1 604 689 7842 or email info@lucaradiamond.com.

Edited by Creamer Media Reporter

Comments

Showroom

Aqs image
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.098 0.157s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: