https://www.miningweekly.com
Africa|Construction|Consulting|Contractor|Conveyors|Copper|Design|Energy|Engineering|Hydropower|Logistics|Mining|Power|PROJECT|Refining|Resources|srk|SRK Consulting|Storage|Surface|Sustainable|System|Technology|Underground|Voith|Infrastructure
Africa|Construction|Consulting|Contractor|Conveyors|Copper|Design|Energy|Engineering|Hydropower|Logistics|Mining|Power|PROJECT|Refining|Resources|srk|SRK Consulting|Storage|Surface|Sustainable|System|Technology|Underground|Voith|Infrastructure
africa|construction|consulting-company|contractor|conveyors|copper|design|energy|engineering|hydropower|logistics|mining|power|project|refining|resources|srk|srk-consulting|storage|surface|sustainable|system|technology|underground|voith|infrastructure

Kamoa-Kakula copper project, Democratic Republic of Congo – update

Image of Kamoa-Kakula mine

20th August 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kamoa-Kakula copper project.

Location
The Kolwezi district of Lualaba province, in the Democratic Republic of Congo (DRC).

Project Owner/s
Kamoa Copper, a joint venture (JV) between base and precious metals developer Ivanhoe Mines, with 39.6% ownership; Zijin Mining Group, with 39.6% ownership; Crystal River Global, with 0.8% ownership; and the DRC government, with 20% ownership.

Project Description
Ivanhoe Mines has announced outstanding economic results in the independent integrated development plan for the tier-one Kamoa-Kakula copper project.

The Kamoa-Kakula Integrated Development Plan 2020 comprises three development scenarios: the Kakula definitive feasibility study (DFS), the Kakula-Kansoko prefeasibility study (PFS) and the Kamoa-Kakula preliminary economic assessment (PEA).

Kakula
The Kakula DFS proposes the development of a Stage 1, six-million-tonne-a-year underground mine and surface processing complex at th Kakula deposit, with a capacity of 7.6-million tonnes a year built in two modules of 3.8-million tonnes a year. For this option, 110-million tonnes will be mined at an average grade of 5.22% copper, producing 8.5-million tonnes of high-grade copper concentrate, containing about 10.8-billion pounds of copper.

Kakula-Kansoko
The Kakula-Kansoko 2020 PFS evaluates the development of mining activities at the Kansoko deposit in addition to the Kakula mine, initially at a rate of 1.6-million tonnes a year, to supply the concentrator at Kakula, eventually ramping up to six-million tonnes a year as the reserves at Kakula are depleted.

Kamoa-Kakula
The Kamoa-Kakula 2020 PEA assesses an additional development option of mining several deposits on the Kamoa-Kakula project as an integrated, 19-million-tonne-a-year mining, processing and smelting complex, built in multiple stages.

An initial six-million-tonne-a-year mining operation will be established at the Kakula mine on the Kakula deposit, which will be followed by a separate six-million-tonne-a-year mining operation at the Kansoko mine. A third six-million-tonne-a-year mine will then be established at the Kakula West mine, in addition to a fourth initial mine in the Kamoa North area operating at one-million tonnes a year. The processing plant will be built in five modules of 3.8-million tonnes a year, with an ultimate capacity of one-million tonnes a year.

As the resources at the Kakula, Kansoko and Kakula West mines are mined out, production will begin sequentially at five other mines in the Kamoa North area to maintain throughput of 19-million tonnes a year to the existing concentrator and smelter complex.

Each mining operation is expected to be a separate underground mine, with a shared processing facility and surface infrastructure located at Kakula. Material will be transported to the Kakula processing complex by a system of overland conveyors. Included in this scenario is the construction of a direct-to-blister copper smelter with a capacity of one-million tonnes of copper concentrate a year.

Potential Job Creation
Once the two processing plants at Kakula are operating, Ivanhoe expects to employ almost 2 000 permanent Kamoa employees.

Net Present Value/Internal Rate of Return
The Kakula DFS yields an after-tax net present value (NPV), at an 8% discount rate, of $5.5-billion and an internal rate of return (IRR) of 77% over a 21-year mine life, with a payback of 2.3 years.

The Kakula-Kansoko PFS yields an after-tax NPV, at an 8% discount rate, of $6.6-billion and an IRR of 69% over a 37-year mine life, with a payback of 2.5 years.

The Kamoa-Kakula PEA yields a potential after-tax NPV, at an 8% discount rate, of $11.1-billion and an IRR of 56% over a mine life of more than 40 years, with a payback of 3.6 years.

Capital Expenditure
The Kakula DFS estimates peak funding at $775-million, remaining initial capital costs at $646-million and expansion capital costs at $594-million.

The Kakula-Kansoko PFS estimates peak funding at $848-million, remaining initial capital costs at $695-million and expansion capital costs at $750-million.

The Kamoa-Kakula PEA estimates peak funding at $784-million, remaining initial capital costs at $715-million and expansion capital costs at $4.46-billion.

Planned Start/End Date
Initial production of copper concentrate at the Kakula Mine processing plant began on May 25, 2021.

The expansion of the Kakula processing plant will be brought forward from the first quarter of 2023 to the third quarter of 2022.

Latest Developments
Commercial production was achieved at the project’s Phase 1 concentrator plant in July 2021.

Kamoa-Kakula’s initial production guidance, on a 100%-project basis, is between 80 000 t and 95 000 t of copper in concentrate for this year.

Ivanhoe reported in August 2021 that construction of Phase 2 of the Kamoa-Kakula project is progressing “slightly ahead of plan” and remained on track for startup in the third quarter of 2022.

Meanwhile, study work to accelerate the Phase 3 mine and concentrator expansion to at least 11.4-million tonnes a year is ongoing. Ivanhoe has said that, based on independent benchmarking, the project’s phased expansion scenario to 19-million tonnes a year “would position Kamoa-Kakula as the world’s second-largest copper mining complex”, with peak copper production of more than 800 000 t/y.

At the end of July, Kamoa-Kakula’s surface ore stockpiles held about 3.5-million tonnes grading 4.77% copper, containing more than 168 000 t of copper.

Ivanhoe, together with its partner Zijin, is exploring the acceleration of the Kamoa-Kakula Phase 3 concentrator expansion, which includes optimisation work to determine mining production capacity and costs at the various mining areas on the Kamoa-Kakula complex, including expanded facilities at the Kansoko mine, Kamoa North (including the Bonanza Zone) and Kakula West.

Kamoa Copper, the company through which Ivanhoe and Zijin hold the Kamoa-Kakula project, is also refining its longer-term downstream processing strategy, including the potential construction of a smelter or hydrometallurgical processing facility.

In April 2021, Ivanhoe Mines Energy DRC entered into an agreement with the DRC's State-owned power company Société Nationale d'Électricité (SNEL) to upgrade a major turbine at the Inga II hydropower facility on the Congo river.

The upgraded turbine is expected to produce 162 MW of clean, renewable hydropower, providing the Kamoa-Kakula copper mine with sufficient, sustainable electricity for future expansions, including a copper smelter.

Ivanhoe Mines Energy extended its existing financing agreement under a public–private partnership with SNEL in August 2021 to upgrade Turbine 5, a major turbine in the existing Inga II hydropower facility.

The extension of this financing agreement builds on the framework agreed in the memorandum of understanding signed with SNEL.

Key Contracts, Suppliers and Consultants
DFS/PFS/PEA:
OreWin (overall report preparation, mining, logistics, power and economic analysis); China Nerin Engineering (smelter design); DRA Global (mine surface infrastructure and metallurgical processing); Epoch Resources (tailings storage facility design); Golder Associates (hydrology models and recommendations); KGHM Cuprum R&D Centre (technical adviser on certain mining methods and geotechnical); Outotec Oyj (smelter technology); Paterson and Cooke (paste backfill plant design and surface/underground paste distribution system); SRK Consulting  (mine geotechnical recommendations); Stantec Consulting International (mining and mineral reserves) and Wood (mineral resources estimation); and Kamoa Copper and SNEL, together with Stucky SA (engineering procurement and construction management – Turbine 5) and Voith Hydro (contractor Turbine 5), have started a technical assessment to define the scope of work and associated costs estimate.

Contact Details for Project Information
Ivanhoe Mines, tel +1604 688 6630 (North America), +27 11 088 4300 (South Africa) or email info@ivanhoemines.com.

Edited by Creamer Media Reporter

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.102 0.156s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: