https://www.miningweekly.com

Ivanhoe starts feasibility study on first phase Platreef project

12th August 2015

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

JOHANNESBURG (miningweekly.com) – TSX-listed Ivanhoe Mines has initiated a feasibility study for the first phase of the development of its Platreef project, in Limpopo.

The study, which kicked off early this month, aimed to build on the positive findings of the prefeasibility study (PFS) completed in January for the construction of an underground mine, concentrator and other associated infrastructure to support initial concentrate production of four-million tonnes a year by 2019.

The Canadian platinum-group metals producer aimed to develop the Platreef platinum, palladium, rhodium, gold, nickel and copper mine in three phases after the PFS confirmed the “excellent” economics and technical viability of the low-cost operation.

The PFS estimated a preproduction capital cost of $1.2-billion, including $114-million in contingencies, to deliver the first phase operation of 433 000 oz of platinum, palladium, rhodium and gold, in addition to 19-million pounds of nickel and 12-million pounds of copper a year.

The company had also progressed site work at the mine that would eventually expand production to eight-million tonnes a year in the second phase, before reaching a steady-state 12-million-tonne-a-year operation in the third phase.

Ivanhoe said it had completed 80% of the work on the electricity substation, which would have an initial capacity of 5 MVA, and power lines from State-owned power utility Eskom, that would be used for the sinking of Shaft 1.

The company expected the operations of Phase 1 to use around 100 MVA when fully operational.

The construction of the large, concrete shaft collar and plenum was under way, while commissioning was under way for the presink winder that would sink Platreef’s Shaft 1 to a depth of around 60 m below surface.

The construction of the foundations for the large winding equipment needed to sink the shaft below 60 m were almost completed.

Shaft 1, which would have an internal diameter of 7.25 m, was projected to reach a total depth of 975 m by 2018.

Other work on site included the construction of the primary terraces for Shaft 1 and the stormwater pond.

Early works, including the boxcut and hitch foundation civil works, on Shaft 2 was also expected to start this year. Shaft 2, which would have an internal diameter of 10 m, would be capable of hoisting six-million tonnes a year.

Edited by Creamer Media Reporter

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.182 0.224s - 106pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: