Impumelelo replacement coal project, South Africa

15th May 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Impumelelo replacement coal project, Mpumalanga, South Africa.

Client
Sasol.

Project Description
The move to develop the mine forms part of what Sasol has previously described as an “intense capital replacement” programme involving four significant projects, namely Thubelisha, Impumelelo, Shondoni and Tweedraai, which will replace the long-serving Twistdraai, Brandspruit, Middelbult and part of the Syferfontein operations respectively.

Impumelelo, in Secunda, Mpumalanga, will replace the old Brandspruit mine and produce coal for the Sasol Synfuels plant.

The project involves the construction of a new 8.5-million-ton-a-year coal mine, which is upgradeable to 10.5-million tons a year.

The No 4 and No 2 coal seams will be mined simultaneously at the project, with the thinner and more complex No 2 seam lying below the No 4. The final shaft depth will be about 225 m below the surface.

After the first section is delivered in 2014, the mine will build up to full production, with 13 continuous miners and six stonework sections in 2019.

The project includes the development of service, ventilation and decline shafts, materials handling systems (including a 28 km overland conveyor, surface surge bunkers, underground conveyors and surge bins) and all the mine infrastructure needed to support operations.

The conveyer system will deliver coal to the Synfuels complex, becoming the longest conveyer system of its kind in the southern hemisphere.

The 11.7-m-diameter men-and-materials shaft will be 210 m deep, with a four-sided station on the No 4 seam.

The 6.7-m-diameter ventilation shaft will also be sunk to 210 m, with access through the four-sided station to the coal production sections.

The shaft complex has been designed to operate for a minimum period of 35 years.

Net Present Value/Internal Rate of Return
Not stated.
 

Value
The project is estimated at R4.6-billion.

Duration
Sasol expects Impumelelo to reach beneficial operation in the first half of this year.

Latest Developments
Sasol Mining has indicated first production from the R4.7-billion Impumelelo mine is expected later this month, followed by the completion of Phase 1 construction in June and the completion of Phase 2 in June 2019.

Key Contracts and Suppliers
RSV Enco-Goba coal joint venture, or JV (engineering, procurement and construction (EPC) management implementation); Murray & Roberts Cementation (men-and-materials and ventilation shafts, as well as decline coal seam development on the No 2 and 4 seams); Concor Civils (subcontracted to provide temporary civil works for sinking and development); ELB Engineering Services (EPC – materials handling conveyor); Veyance Technologies (manufacture and delivery of steel cord conveyor belting); Cascade Logistics (transportation of belt rolls) and Goodyear Engineered Products (cover compound).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Sasol group media manager Alex Anderson, tel + +27 71 600 9605 or email alex.anderson@sasol.com.
RSV Enco-Goba JV, tel +27 11 498 6010, fax + 27 11 498 6210 or email enco@rsvenco.com.

Edited by Creamer Media Reporter

Comments

 

Showroom

SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.135 0.191s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: