Hummingbird secures $5m facility extension for Yanfolila development

1st September 2015

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Aim-listed gold production, development and exploration company Hummingbird Resources has secured a $5-million facility extension to start moving its flagship 1.8-million-ounce Yanfolila gold project, in Mali, towards targeted production in 2016.

With the completion of the initial earthworks, including the excavation, placement and compaction of more than 80 000 m3 of fill materials, Taurus Funds Management expanded its $10-million bridge facility to $15-million to kick off the full construction and ongoing development activities at the emerging mine.

"The extension of the bridge facility allows Hummingbird to maintain its schedule as we conclude all the necessary technical, financial and legal due diligence prior to first draw on the main facility,” CEO Dan Betts told shareholders in an update to the market on Tuesday.

Hummingbird would use the proceeds to start the initial pit dewatering, acquire land around the mine site and finalise the due diligence in preparation for a full draw down of the main $75-million facility with Taurus.

“We continue to believe that the development of Yanfolila during the downturn will set Hummingbird apart as a cash-generative miner offering investors leveraged exposure into the gold space,” explained Taurus director of management Nick Farr-Jones.

Edited by Creamer Media Reporter

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
Universal Storage Systems (SA)
Universal Storage Systems (SA)

South African leader in Steel -Racking, -Shelving, and -Mezzanine flooring. Universal has innovated an approach which encompasses conceptualising,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.272 0.314s - 107pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: