Name of the Project
Grootegeluk 6 (GG6) expansion project.

Location
Limpopo, South Africa.

Project Owner/s
Exxaro Resources.

Project Description
The project entails the expansion of the existing Grootegeluk 2 plant to enable the production of 1.7-million-tonne-a-year to 2.7-million-tonne-a-year semisoft coking coal.

Potential Job Creation
Up to 2 000 contract positions at peak construction. Around 100 permanent positions once the plant is in operation.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
R4.8-billion.

Planned Start /End Date
First production is expected in the second half of this year (2019), with full production expected by the end of 2020.

Latest Developments
As a result of the Group Five contract being terminated in March 2019, a procurement process for the full Group Five scope of work has been concluded, contracts awarded and full construction activities were expected to start in July 2019.

The project team, together with operations, is working on action plans to minimise any volume and value impact caused by the expected three to six months’ delay.

Key Contracts and Suppliers
SMEI, Stefstocks Joint Venture, thyssenkrupp.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Exxaro Resources executive head: strategy and stakeholder engagement Mzila Mthenjane, tel +27 12 307 7393 or  email investorrelations@exxaro.com.

Edited by Creamer Media Reporter

Comments

 

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 17 May 2024
17th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.159 0.21s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: