Gold Road picks a development option for Gruyere

3rd August 2015

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

KALGOORLIE (miningweekly.com) – The Stage 1 prefeasibilty study (PFS) into the Gruyere gold project, in Western Australia, has selected a 7.5-million-tonne-a-year throughput rate as the most effective, giving the project a potential mine life of 10 to 15 years.

The Stage 1 PFS also identified a gas-fired power generation plant as the preferred power source, over diesel and trucked liquefied natural gas.

Project owner Gold Road Resources on Monday said the Gruyere project would have average gold production of 250 000 oz/y over its mine life, based on a mineral resource of 137.8-million tonnes, grading 1.24 g/t gold for 5.51-million ounces.

The project would comprise an openpit truck and shovel operation, with all mining operations being done by contractors. The process plant and infrastructure would be owner-operated and managed.

“The detailed work that our team has undertaken allows us to confidently determine the best option for Gruyere is a production rate of 7.5-million tonnes a year, using a semi-autogenous grinding and ball mill circuit, combined with gas delivered by pipeline as the preferred fuel source for power,” said Gold Road executive chairperson Ian Murray.

Having established the study parameters, Gold Road was now progressing the Gruyere PFS, which would include capital and operating cost estimates, plant layout design, metallurgical testwork, tailings storage facility option studies, as well as starting native title discussions.

The final PFS was due for completion in the March 2016 quarter.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest Multimedia

Photo of Martin Creamer
On-The-Air (26/04/2024)
Updated 2 hours 12 minutes ago By: Martin Creamer

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.923 0.96s - 107pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: