https://www.miningweekly.com
Africa|Construction|Design|Financial|Gold|Infrastructure|PROJECT|Storage|Surface|Underground|Water|Equipment|Environmental|Infrastructure|Operations
Africa|Construction|Design|Financial|Gold|Infrastructure|PROJECT|Storage|Surface|Underground|Water|Equipment|Environmental|Infrastructure|Operations
africa|construction|design|financial|gold|infrastructure|project|storage|surface|underground|water|equipment|environmental|infrastructure|operations

Far West Gold Recoveries operation, South Africa – update

Operations at the FWGR

Photo by DRDGOLD

22nd September 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Far West Gold Recoveries (FWGR) operation.

Location
Gauteng, South Africa.

Project Owner/s
DRDGOLD’s acquisition of Sibanye-Stillwater’s (Sibanye’s) West Rand Tailings Retreatment Project assets was finalised on July 31, 2018. Following the successful implementation of the transaction between the two companies, Sibanye owned 38.05% of the issued share capital of DRDGOLD.

Under the terms of the transaction, entered into in November 2017, Sibanye agreed to exchange selected surface-gold processing assets and tailings storage facilities (TSFs) for shares in DRDGOLD.

Sibanye also had an option to subscribe for further shares in DRDGOLD within 24 months at a 10% discount. In January 2020, Sibanye exercised this option, obtaining a 50.1% controlling interest in DRDGOLD.

Project Description
FWGR is being rolled out in a phased approach.

Phase 1 included early-stage production, involving upgrading the Driefontein 2 plant to process tailings from the Driefontein 5 dump at between 400 000 t and 600 000 t a month, and depositing the residue on the Driefontein 4 tailings dam, which was upgraded to a cyclone deposition dam to cater for the higher throughput.

Phase 2 envisages the construction of a high-volume central processing plant capable of processing between 1.2-million and 2.4-million tonnes a month, the continued use of Driefontein 2 plant at an increased 600 000 t a month, and the development of a new regional TSF capable of receiving up to three-million tonnes a month to a capacity of about 800-million tonnes.

In this phase, reclamation will initially be from the Driefontein 3, Libanon and Kloof 1 dumps, and then from the Ventersdorp North and South dumps. The scale of the infrastructure established in this phase will allow for the reclamation from other sources in the region. The objective is to clean up the regional landscape by reprocessing tailings that are currently on dolomite, and redeposit the reclaimed material onto a properly designed and managed megadam, thereby reversing the potential pollution of underground water in the region.

Phase 2 is expected to extend the life of the operation to 20 years and beyond, and good progress has been made in advancing this phase, with DRDGOLD well into the planning and permit application processes.

As an alternative to Phase 2, or if Phase 2 is delayed, Phase 1 can be extended

by extending deposition onto the Driefontein 4 tailings dam, owing to the good cyclone splits being achieved at the tailings dam. Envisaged is the treatment of the remaining tonnes from Driefontein 5 and then processing material from Driefontein 3.

Potential Job Creation
Since its inception, FWGR has secured employment for more than 150 employees and is committed to its environmental, social and governance mandate, as well as social upliftment programmes, in the far West Rand area of operations. With the implementation of Phase 2 and extended life-of-mine (LoM), more opportunities are expected to create DRDGOLD’s value creation narrative.

Capital Expenditure
DRDGOLD invested R330-million of capital in Phase 1.

The cost of Phase 2 will depend on whether the company chooses to build a second plant and TSF or expand the existing facilities.

Planned Start/End Date
Phase 1 commercial production began within eight months of the acquisition, on April 1, 2019, and made its maiden full 12-month contribution to DRDGOLD’s financial results in the 2020 financial year.

Construction of Phase 2 is planned to be completed by 2024/5, provided the requisite amendments to existing regulatory approvals are obtained, the gold market remains favourable and an investment climate prevails that is conducive to long-term investment on this scale.

Latest Developments
DRDGOLD has reported in its results for the financial year ended on June 30, 2023, that there had been delays in the supply to of imported equipment to FWGR.

FWGR produced 1 351 kg of gold in the 2023 financial year (FY2022: 1 564 kg), as a result of the lower tonnage and yield achieved. The lower tonnage was because of Driefontein 5’s nearing the end of its LoM and entering final clean-up.

Operational delays occurred in the commissioning of Driefontein 3 that was initially earmarked to replace the expected lower tonnages from Driefontein 5.

In addition, severe rainstorms occurred in December 2022 and February 2023, leading to disruptions.

DRDGOLD further reports in its results that a revised design for the regional tailings storage facility was submitted to the DWS in May 2023 in support of an application to amend the conditions of the water-use licence of the proposed facility.

Key contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
R&A Strategic Communications on behalf of DRDGOLD Jane Kamau, tel +27 11 880 3924 or email jane@rasc.co.za.

Edited by Creamer Media Reporter

Comments

Latest News

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.125 0.18s - 95pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: