Elementos's Cleveland proves its mettle

20th August 2015

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – The proposed Stage 2 openpit operation planned for the Cleveland mine would add an additional A$21-million to the project’s cash flow, owner Elementos reported on Thursday.

Elementos was developing the Cleveland project through a staged, low-capital development strategy, which the company hoped would minimise up-front capital, with cash flow funding future stages.

A recent prefeasibility study into the Stage 1 tailings project estimated that an initial capital investment of A$21-million would be required to deliver some 5 200 t of tin concentrate and 1 500 t of copper concentrate over a seven-year mine life.

A scoping study into the Stage 2 openpit operation was based on a mineral resource of 800 000 t, grading 0.81% tin and 0.27% copper, over five pits, which would be mined at a combined rate of 200 000 t/y, over a three-year period.

The incremental capital cost required for the Stage 2 operation was A$6.6-million but this would be fully funded by cash flow from the Stage 1 operations, Elementos said.

While production from the Stage 1 tailings operation was scheduled to start in 2016 or 2017, the Stage 2 operation would start in 2017.

Elementos CEO Tim McManus said on Thursday that the openpit scoping study provided a strong endorsement to the staged development strategy being considered at Cleveland.

“Work is also continuing on the Stage 3 underground operation, which has the potential to significantly expand the project cash flow and mine life,” he added.

The Stage 3 underground operation was expected to come on line in 2021.

Meanwhile, McManus was hopeful that the Cleveland operation could offer considerable exploration upside, as the technical studies at the project were currently based only on the validated work of the previous mine operator.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.129 0.174s - 112pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: