Company Announcement: PFS results for PhosEnergy Process

5th March 2013

  

Font size: - +

This article has been supplied as a media statement and is not written by Creamer Media. It may be available only for a limited time on this website.

Uranium Equities Limited  (0.45 MB)

Uranium Equities is pleased to announce that, utilising design data gathered during successful Demonstration Plant operations carried out in 2012, an independent Pre-Feasibility Study (PFS) level Engineering Study of the PhosEnergy Process has supported the viability and low-cost nature of the Process for extracting uranium as a by-product from phosphate fertiliser production. The Study, which UEQ and Cameco commissioned through a global engineering and professional services consultancy, estimated a capital cost of US$156 million for a base case PhosEnergy plant located at the site of a 1Mtpa P2O5 phosphate facility in the south east United States capable of producing approximately 880,000 pounds of uranium per annum at an estimated cash operating cost of less than US$18 per pound.

In UEQs opinion, even at current spot uranium prices, a facility of this nature would be capable of generating strong cash operating margins – highlighting the robust economics of the PhosEnergy Process and its potential to underpin an exciting business opportunity for UEQ and its partner, Cameco Corporation. Following receipt of the PFS Cameco has committed to pursuing the next key phase of development of the jointly owned PhosEnergy Process by committing a further US$4 million to the project.  This investment finalises Cameco’s earn into 73 per cent of the technology with UEQ retaining a 27 per cent interest. “This is a great result which follows a highly successful Demonstration Plant test program in the United States last year,” said UEQ’s Managing Director, Bryn Jones.

“This clearly indicates the robust nature of the process and its ability to produce uranium at a cash operating cost which would be well within the lowest cost quartile for uranium producers globally,” Mr Jones said. “The next phase of commercialisation is expected to comprise an on-site demonstration of the PhosEnergy Process at the site of an existing phosphate producer in North America, and this phase will underpin a Definitive Feasibility Study and enable us to address full scale commercialisation from the PhosEnergy Process,” Mr Jones noted. “The continued financial support of Cameco is indicative of not only the robustness of the PhosEnergy Process the engineering completed to date but also the commercial opportunities represented by the PhosEnergy Process,” He added.

PFS Level Engineering Study

Utilising information gathered during the technical development of the PhosEnergy Process – in particular the successful Demonstration Plant operations announced on 19th September 2012 – the Study has defined capital and operating cost estimates for a PhosEnergy plant located at the site of a nominal 1M short tonne P2O5 phosphate facility in the south east United States producing approximately 880,000 pounds of uranium per annum (Base Case).

Using the outputs of the PFS, estimated project costs are as follows:

•Estimated cash operating costs of less than US$18 per pound of U3O8; and
•Estimated capital cost of US$156 million for the Base Case PhosEnergy plant.

Depending on the (normally) available infrastructure at the development site, additional capital may be required (estimated up to US$9 million for a plant in south east USA). In UEQs opinion the results of the PFS put the PhosEnergy Process in the bottom quartile for operating costs of all uranium production worldwide and at a considerable cost advantage over the bulk of new projects likely to come online over the next 5 to 10 years.

Cash Operating Cost Estimate

Cash operating costs were derived using a methodology consistent with achieving an accuracy of +50%/-30% and an AACE Class IV estimate. The Study estimated operating costs to produce an intermediate product which can be toll-milled through any one of a number of facilities in the United States, for which quotes have been received. The estimated cash operating cost including toll milling and product transport is estimated at less than US$18 per pound of U3O8 including contingency.

Intermediate product transport for toll-milling accounts for a substantial portion of the total cash operating costs. This represents a significant opportunity for cost-structure improvements both through improved contractual transport arrangements and contained uranium concentration of the intermediate product.

Other opportunities exist in the refinement of reagent usage and power consumption as the development progresses. Estimated operating costs do not include corporate office, marketing and downstream phosphate processing costs which may be incurred. The estimated operating costs will form the basis of commercial negotiations with potential phosphate partners.

Capital Cost Estimate

The capital cost estimate was derived from Process Flow Diagrams (PFDs), site plans, General Arrangements (GAs) and a detailed mechanical equipment list.  Depending on the phosphate facility targeted for commercialisation, there may be additional capital required for infrastructure such as electrical sub-stations and reagent storage. It is estimated that these additional capital items may cost up to US$9 million for a facility in the south east USA. Several opportunities for further optimising equipment, structural and civil capital components are under review and will be incorporated into subsequent studies.    

Next Steps in Commercialisation

Discussions are continuing with phosphate producers to allow on-site demonstration of the PhosEnergy Process using the existing containerised Demonstration Plant.
This Demonstration Plant operation will allow for further refinement of capital and operating cost numbers and provide sufficient inputs to enable a Definitive Feasibility Study (DFS) to be completed. Commercial discussions around the split in revenue on a commercial application of the PhosEnergy Process on an operating phosphate facility will be required to allow an investment decision to progress the project further.

These commercial negotiations will consider the capital risk taken by both parties, the phosphate producer’s appetite for exposure to the uranium market and the long mine life of phosphate projects – generally over 20 years. The initial focus for commercialisation is expected to be the phosphate fertiliser industry in the USA, where UEQ estimates there is an opportunity to recover approximately 6 million pounds of uranium per annum. Operating in the USA also has several potential synergies with Cameco’s existing US operations. The worldwide PhosEnergy production opportunity is in the region of 20 million pounds of uranium per annum.

Cameco commits further US$4 million for further development

Cameco Corporation, which is a leading uranium producer and supplier of nuclear fuel services, has completed its earn-in of 73 per cent of the PhosEnergy Process by committing to a further investment of US$4 million. These funds will be used for further development of the PhosEnergy Process and should be sufficient to carry the project through completion of a Definitive Feasibility Study.Cameco has also agreed to fund at least 50 per cent of UEQ’s proportionate share of first facility capital requirements on terms to be agreed.
 

Edited by Creamer Media Reporter

Comments

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.136 0.171s - 89pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: