https://www.miningweekly.com
Construction|Design|Engineering|Environment|Export|Financial|Fluor|Logistics|Mining|Modular|Pipelines|Power|PROJECT|Resources|Water|Equipment|Products|Solutions|Environmental|Infrastructure|Operations
Construction|Design|Engineering|Environment|Export|Financial|Fluor|Logistics|Mining|Modular|Pipelines|Power|PROJECT|Resources|Water|Equipment|Products|Solutions|Environmental|Infrastructure|Operations
construction|design|engineering|environment|export|financial|fluor|logistics|mining|modular|pipelines|power|project|resources|water|equipment|products|solutions|environmental|infrastructure|operations

Colluli potash project, Eritrea

22nd February 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Colluli potash project.

Location
Eritrea.

Client
The project is 100%-owned by the Colluli Mining Share Company (CMSC), a 50:50 joint venture between Danakali and the Eritrean National Mining Corporation.

Project Description
In a front-end engineering design (FEED) study completed in January 2018, the Colluli project was established as the most advanced, economically attractive and fundable sulphate of potash (SoP) greenfield development project globally.

The project has a Joint Ore Reserves Committee- (Jorc-) compliant mineral resource estimated at 1.29-billion tonnes grading at 11% potassium oxide (K2O) for 260-million tonnes of contained SoP equivalent.

The Jorc-compliant ore reserve is estimated at 1.1-billion tonnes grading at 10.5% K2O for 203-million tonnes of contained SoP equivalent.

A modular development approach for the Colluli project has shown a highly scalable, long-life project. The shallow mineralisation of the project makes the resources amenable to opencut mining.

The mine will comprise one openpit developing progressively from north-east to south-west. The pit will have a progressive working face that will provide access to each of the mineralised layers simultaneously. The orebody comprises  sylvinite, carnallitite and kainitite, which will be fed as orefeed into the processing plant and from which sylvite, carnallite and kainite will be extracted and mixed to produce SoP.

The project proposes two modules.

Module 1 is expected to produce 472 000 t/y of premium sulphate of potash product (SoP).

Module 2, starting production in Year 6 of the project, will increase total SoP production to 944 000 t/y.

Mining will be conducted by mining contractors using conventional mechanised equipment, with no drill-and-blast required. Mined ore will be transported by truck to a run-of-mine pad adjacent to the processing plant.

The massive Colluli ore reserve has significant capacity to underpin further expansions and support decades of growth beyond modules 1 and 2.

Colluli has significant diversification potential beyond SoP, including the option to produce additional potash and salt products such as muriate of potash, SoP-magnesia, kieserite, gypsum, magnesium chloride and rock salt.

At FEED production rates, the project has an expected mine life of 200 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 10% discount rate, of $902-million for modules 1 and 2, and an internal rate of return of 29.9%. Module 1 has a payback of 3.25 years.

Value
Module 1 will require an initial capital investment of $302-million. The incremental Module 2 development is expected to require an initial capital investment of $202-million.

Duration
Not stated.

Latest Developments
Danakali reported in its quarterly report for the period ended December 31, 2018, released in January this year, that Colluli is execution ready.

Danakali and CMSC are focused on logistics and other technical collaboration aspects with offtake partner EuroChem, as well as on operational contracts, operations readiness, funding and corporate social responsibility initiatives.

In December 2018, CMSC executed a mandate to provide fully underwritten debt finance facilities of $200-million to fund the construction and development of Colluli.

African Export-Import Bank (Afreximbank) and Africa Finance Corporation (AFC) are acting as mandated lead arrangers, which is a critical project financing and execution milestone for CMSC and Danakali.

Danakali and its debt adviser, Endeavour Financial, are working with the mandated lead arrangers to advance their due diligence, which is necessary to obtain credit approval.

The mandated lead arrangers and their advisers are also reviewing the provisions of the draft commercial contracts – engineering, procurement and construction management, and power and mining – as they become available.

A site visit to Colluli by the mandated lead arrangers and their advisers is expected to take place in the March 2019 quarter.

Key Contracts and Suppliers
Fluor (FEED engineering lead, metallurgy, process and nonprocess infrastructure, and capital and operating cost estimates); AMC Consultants (mine – geotechnical, mine design, mine contract tendering support, compilation of mining costs and competent persons report, and ore reserve update); Knights Piésold (evaporation ponds and tailings, infrastructure geotechnical investigations and hydrogeological investigation and modelling); Global Potash Solutions and Elemental Engineering (metallurgy and processing technical support); Ausenco (water abstraction and pipelines); Braemar ACM (port capacity, capability and handling fees, and engagement of shipping lines); and MBS Environmental (social and environment).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Danakali, tel +61 8 6315 1444, fax +61 8 9467 9119 or email info@danakali.com.

Edited by Creamer Media Reporter

Comments

 

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 17 May 2024
17th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.192 0.247s - 95pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: