Coburn mineral sands project, Australia – update

2nd October 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Coburn mineral sands project.

Location
The project is located in the Gascoyne region of Western Australia.

Project Owner/s
Strandline Resources.

Project Description
An updated definitive feasibility study (DFS) has resulted in significant increases in forecasted financial returns for the project over an initial 22.5-year mine life.

The project has Joint Ore Reserves Committee-compliant ore reserves of 523-million tonnes grading 1.11% total heavy minerals for about 5.8-million tonnes of contained heavy mineral.

The mining study has confirmed a conventional openpit dry mining operation where free-dig unconsolidated sand is mined using heavy mobile equipment to transport material to dozer mining units. The units prepare the ore for processing and the ore is pumped in slurry form to the processing plant.

Bulk metallurgical testwork of representative samples using full-scale or scalable processing equipment has confirmed conventional processing capable of producing high-quality products, with exceptional pit-to-product recovery rates achieved within concentrate and the final product streams.

The DFS has further confirmed an efficient and modern process design capable of producing a high-grade saleable 95% heavy mineral concentrate product from the wet concentration plant, and final products through further processing by the mineral separation plant.

The project will produce four final products comprising a premium zircon product (66% zirconium dioxide), zircon concentrate product (which contains payable zircon, titanium and monazite minerals), rutile product (93% titanium dioxide) and a chloride-grade ilmenite product (62% titanium dioxide).

The updated DFS is still based on a throughput of 23.4-million tonnes a year, with an average production of 34 000 t/y of zircon, 54 000 t/y of zircon concentrate, 110 000 t/y of chloride ilmenite and 24 000 t/y of rutile, which are expected to supply about 5% of the global zircon market.

There is potential to further increase project reserves and mine life by about 15 years – to 37.5 – years through the conversion of resources extending north and along strike of the current ore reserves.

Potential Job Creation
Peak workforce during construction is estimated to be more than 300 people, with an average operational workforce during production of about 150 direct skilled workers.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of A$705-million, up from A$544-million in the feasibility study. The pretax internal rate of return has increased from 32% to 37%.

The project has a payback of 2.1 years.

Capital Expenditure
Capital expenditure has increased from A$257-million in the DFS to A$260-million in the updated DFS.

Planned Start/End Date
The project will take 18 months to design and build to achieve first ore to the process plant.

Latest Developments
Primero Group has been awarded preferred engineering, procurement and construction (EPC) status at Strandline Resources’ Coburn mineral sands project.

The EPC work will amount to about A$150-million in revenue for Primero, and will cover the EPC, and commissioning and performance testing of the wet concentration plant, mineral separation plant and associated processing circuits.

Strandline MD Luke Graham has said that the appointment of Primero marks another key step in the company’s strategy to bring the Coburn project into production and establish an important relationship with leading service providers.

The full project award is subject to Strandline taking a final investment decision in the coming months.

Strandline earlier this month awarded a A$21-million fixed-price contract to supply in-pit dozer mining units for the Coburn project, and has previously announced a series of binding offtake agreements at the project with consumers in America, Europe and China.

Key Contracts, Suppliers and Consultants
R Engineering Services, AMC Consultants, IHC Robbins, AECOM and TZMI’s Allied Mineral Laboratories (DFS); SRK Consulting (technical due diligence of engineering designs and planning associated with geology, hydrology, mining, processing, infrastructure, logistics, implementation strategies, cost estimates and environmental, social and permitting); Deloitte Access Economics (independent economic cost-benefit analysis); TZ Minerals International (product quality and marketing); and Macmahon (construction of road access and bulk earthworks); Piacentini & Son (in-pit dozer mining units); and Primero (EPC and commissioning and performance testing of the wet concentration plant, mineral separation plant and associated processing circuits).

Contact Details for Project Information
Strandline Resources, tel +61 8 9226 3130 or email enquiries@strandline.com.au.

Edited by Creamer Media Reporter

Comments

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.108 0.167s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: