https://www.miningweekly.com
Construction|Crushing|Engineering|Filtration|Flow|Gold|Infrastructure|Installation|Mining|PROJECT|Refining|Services|System|Water|Flow|Solutions|Infrastructure|Operations
Construction|Crushing|Engineering|Filtration|Flow|Gold|Infrastructure|Installation|Mining|PROJECT|Refining|Services|System|Water|Flow|Solutions|Infrastructure|Operations
construction|crushing|engineering|filtration|flow-company|gold|infrastructure|installation|mining|project|refining|services|system|water|flow-industry-term|solutions|infrastructure|operations

Castle Mountain gold project, US

8th November 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Castle Mountain gold project.

Location
San Bernardino County, California, in the US.

Client
Equinox Gold.

Project Description
The Castle Mountain gold mine produced more than one-million ounces of gold as an openpit heap-leach mine from 1992 to 2004, when production ceased, owing to low gold prices, and the mine was substantially reclaimed.

A prefeasibility study (PFS) has determined that Castle Mountain can be developed as a low-cost heap-leach gold mine. The project has proven and probable reserves of 197.6-million tonnes grading 0.56 g/t.

The project will be developed in two phases.

The phased ramp-up approach enables Equinox to use existing permits to expedite production while completing the feasibility study and permitting for the Phase 2 expansion. While Phase 2 will operate within the existing permitted mine boundary, the increased mining and water extraction rates will require updated permitting for the project.

Under the PFS mine plan, Phase 1 of the project will produce an average of 45 000 oz/y of gold over three years. Phase 2 production is expected to average 203 000 oz/y of gold for 13 years.

Total production is estimated at 2.8-million ounces over a 16-year mine life, with expansion potential from existing near-mine mineralisation.

Phase 1 will comprise a run-of-mine (RoM) heap-leach operation processing primarily 12 700 t/d of stockpiled ore from previous operations. Phase 2 will increase throughput to 41 000 t/d of ore, of which 2 340 t/d of higher-grade ore will be processed through a milling circuit.

Phase 1 processing operations will treat the solutions from the RoM heap-leach facility operating in a new adsorption, desorption and refining (ADR) plant capable of treating 400 m3/hr of pregnant solution to produce doré bars.

Phase 2 will require an expansion of the solution handling and ADR plant capacity to receive the additional flow from the increased RoM heap-leaching operations and loaded carbon from the carbon-in-leach (CIL) plant. The Phase 2 CIL circuit will comprise a three-stage crushing circuit, ball mill, gravity circuit, CIL circuit, cyanide destruction circuit and mill fines filtration circuit, as well as an Acacia high-intensity leach circuit.  The comminution circuit is designed to achieve 80% passing 150 μm. Loaded carbon from the CIL circuit will be treated in RoM desorption and recovery circuits. The expanded plant will have capacity to treat 1 900 m3/hr to produce doré bars.

The heap-leach pads for both phases will be double-synthetic-lined using a 2 mm linear low-density polyethylene liner, with a leak detection and recovery system between the synthetic liners. Spent heap-leach ore from prior operations will be used to form a 600 mm drainage layer above the lining system. Ore will be stacked in 15 m lifts with no interlift liners. Heap irrigation, at a nominal rate of 10 ℓ/hr/m2, will be delivered through buried drip lines to reduce evaporative losses of solution.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 5% discount rate, of $406-million and an after-tax internal rate of return of 20%.

Value
Total project capital expenditure is estimated at $347-million – Phase 1 will cost $58-million to implement and Phase 2 $295-million.

Duration
Phase 1 ore is targeted for the third quarter of 2020.

Latest Developments
The Equinox Gold board has approved the start of Phase 1 construction at Castle Mountain openpit gold mine, while studies continue on a 200 000 oz/y Phase 2 expansion.

Early works construction has been under way at the project since the third quarter, with activities to date having focused on detailed engineering, procurement, installation of piping and other infrastructure, as well as heap-leach earthworks.

The company expects to start installation of leach pad liners in November, with first gold pour targeted for the third quarter of next year.

The Phase 2 feasibility study is under way, with completion targeted for the second half of 2020, at which point Equinox will submit the application to amend its existing plan of operations and permits to support the Phase 2 expansion.

Key Contracts and Suppliers
Kappes Cassiday & Associates, supported by Mine Technical Services, Global Resource Engineering, Call & Nicholas, Geo-Logic Associates and Lilburn Corporation (PFS).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Equinox Gold, tel +1 604 558 0560 or email info@equinoxgold.com.

Edited by Creamer Media Reporter

Comments

Showroom

Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.112 0.166s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: