Cascabel copper/gold/silver project, Ecuador – update

Aerial view of the Cascabel project

Photo by SolGold

3rd November 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Cascabel copper/gold/silver project.

Location
Northern Ecuador.

Project Owner/s
Exploraciones Novomining, an 85%-owned subsidiary of SolGold.

Project Description
A prefeasibility study (PFS) has concluded that Cascabel has the potential to be a large, low-cost and long-life mining operation based on achievable, proven and tested mining and processing assumptions.

The mine is expected to produce a clean copper/gold/silver concentrate, to be sold to Asian and European smelters as part of a project construction financing package.

The project has an initial mineral reserve of 558-million tonnes containing 3.3-million tonnes of copper grading 0.58%, 9.4-million ounces of gold grading 0.52 g/t, and 30-million ounces of silver grading 1.65 g/t over an initial 26-year life-of-mine (LoM), with a potential LoM upside of more than 50 years following the initial LoM.

Access to the Alpala underground mine is expected to be through twin declines,  starting from a boxcut near the surface and the first lift near the 300mRL. Block cave mining will be applied to the underground resource while all horizontal development will be undertaken using conventional drill-and-blast methods. The vertical development for the main ventilation rises will be excavated using blind sinking methods.

The crushed ore from the underground primary crushers will be conveyed to the surface and fed to the secondary crushing circuit. The product from the secondary crushing area will be transferred to the fine ore stockpile, and subsequently reclaimed to the high-pressure grinding rolls (HPGR) circuit.

The product from the HPGR circuit will be transferred to a grinding circuit comprising ball mills that operate in closed circuit with a hydrocyclone cluster.

The project is initially expected to produce about 132 000 t/y of copper, 358 000 oz/y of gold and one-million ounces of silver (212 000 t/y copper equivalent), with peak copper production of 210 000 t/y (319 000 t/y copper equivalent).

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an estimated pretax net present value, at an 8% discount rate, of $5.2-billion and an internal rate of return of 25.3%, with a payback of 4.7 years from the start of operations.

Capital Expenditure
$2.7-billion for the initial cave development, first process plant module and infrastructure.

Planned Start/End Date
Construction of the mine is expected to start in 2025, with operations starting in 2030.

Latest Developments
SolGold is in discussions with several “highly credible” groups interested in the Cascabel copper project.

More than 20 active confidentiality agreements are in place and more than five groups have already completed site visits, with several follow-up visits being scheduled.

“External groups evaluating the project are being very diligent in their review as they progress through various stages in their internal processes. In parallel, we continue to advance and derisk Cascabel to position it as a turnkey asset,” CEO and president Scott Caldwell has said.

Key Contracts, Suppliers and Consultants
Mining Plus (mineral resources and reserves estimates); Knight Piésold (environment, social, tailings and water studies); Wood (metallurgy, process plant and infrastructure, as well as financial evaluation); and Wood Mackenzie (marketing).

Contact Details for Project Information
SolGold, tel +44 20 3823 2130 or email investors@solgold.com.au.

Edited by Creamer Media Reporter

Comments

Latest News

Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.11 0.163s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: