https://www.miningweekly.com
Africa|Coal|Construction|Contractor|Design|Energy|Engineering|EPCM|Freight|Mining|Power|PROJECT|rail|Resources|Road|SECURITY|Services|supply-chain|Surface|Transnet|Waste|Water|Maintenance|Environmental|Infrastructure|Waste
Africa|Coal|Construction|Contractor|Design|Energy|Engineering|EPCM|Freight|Mining|Power|PROJECT|rail|Resources|Road|SECURITY|Services|supply-chain|Surface|Transnet|Waste|Water|Maintenance|Environmental|Infrastructure|Waste
africa|coal|construction|contractor|design|energy|engineering|epcm|freight|mining|power|project|rail|resources|road|security|services|supply chain|surface|transnet|waste-company|water|maintenance|environmental|infrastructure|waste

Boikarabelo coal project, South Africa – update

16th April 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Boikarabelo coal project.

Location
Waterberg region in Limpopo, South Africa.

Project Owner/s
Ledjadja Coal Limited (LCL), in which energy company Resource Generation (Resgen) has 74% shares held through wholly-owned subsidiary Resgen Africa Holdings (RAHL).

Project Description
The Boikarabelo coal reserves were estimated at 267.1-million tonnes as at June 30, 2018.

The Boikarabelo coal seam is between 20 m and 30 m below the surface, allowing for low-cost, opencut mining. The seam is between 100 m and 120 m thick, with zones of varying-quality thermal and soft coking coal.

In February 2016, Resgen implemented a revised mine plan. This followed a technical review of the geological model by its technical committee comprising in-house and external experts, who suggested that the revised plan could achieve more than previously expected. The plan is based on selective mining and in-pit dumping to maximise productivity, reduce operating costs and minimise any environmental impact.

The company also implemented a project execution strategy, which transfers mine construction risk, through the appointment of a small number of reputable engineering, procurement and construction contractors with substantial balance sheets, which will allow for recourse in the event of failure or delay.

The mine will be developed using a two-phased approach to limit upfront capital expenditure.

Stage 1 will deliver about 15-million tonnes of run-of-mine coal a year, which will equate to about six-million tonnes of product coal. Of this, about 3.6-million tonnes will be exported and about 2.4-million tonnes will be used domestically.

Stage 2 will involve ramping up production to 12-million tonnes of product thermal coal. It is estimated that fully funded Phase 2 construction and production will not begin before 2025.

The project includes a 44 km rail link to the existing rail network.

To expand the Boikarabelo project’s economic base, a bankable feasibility study on a potential 300 MW independent mine-mouth power station will be completed once the Boikarabelo mine has been commissioned.
 
Potential Job Creation

The project is expected to create 2 500 jobs in the construction phase and 709 full-time jobs.

Net Present Value/Internal Rate of Return
The project has an internal rate of return of 17%.

Capital Expenditure
The estimated capital cost for the project is $300-million.

Planned Start/End Date
First coal deliveries are scheduled for the fourth quarter of 2022.

Latest Developments
Resgen has been granted a waiver by the ASX for Listing Rule 10.1, which enables it to include the further $993 000 in funding agreed with energy supply chain company Noble Resources International.

One of the conditions of the further extension to the facility agreement is that the amount provided under the extension be secured by the existing share pledge granted in favour of Noble over Resgen’s interest in 74% of the shares in Ledjadja.

As Noble is a substantial shareholder in Resgen, grant of the security must comply with ASX Listing Rule 10.1. The original grant of the share pledge to Noble (securing up to $41.9-million in advances as agreed in October 2018) was approved by shareholders for the purposes of the listing rule at the 2018 annual general meeting.

The extension of any further amounts under the facility agreement can, however, be secured only under the share pledge by first obtaining a waiver of ASX Listing Rule 10.1 from the ASX or by calling a meeting and obtaining further shareholder approval.

Resgen submitted an application to ASX in March, seeking a further waiver from the application of ASX Listing Rule 10.1.

Approval of the listing rule waiver enables Resgen to finalise the conditions precedent for immediate drawdown under the facility agreement and increase the amount secured by the share pledge to $51.06-million, plus accrued interest.

The additional funds under the facility agreement will be available to Ledjadja Coal until May 1.

Key Contracts, Suppliers and Consultants
Digby Wells Environmental (mining right application, mine-waste licence, environmental authorisation process for power plant); Sedgman (design, engineering, procurement and construction contract for the coal handling preparation plant, the ongoing operation and maintenance of the plant, and construction of the ancillary works pertaining to the infrastructure of the mine); RCE (rail design and construction, engineering, procurement and construction management, or EPCM, services); NuWater (water EPCM services); EHL Energy (transmission lines), Stefanutti Stocks (preferred mining contractor), Stefanutti Stocks Road and Earthworks (rail earthworks and bridges) and Transnet Freight Rail (ballast, track and signalling).

Contact Details for Project Information
Resgen, tel +27 11 010 6310, fax +27 86 539 3792 or email info@resgen.com.au.

Edited by Creamer Media Reporter

Comments

Showroom

Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 17 May 2024
17th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.142 0.203s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: