https://www.miningweekly.com

Bakubung platinum-group metals project, South Africa

1st February 2013

By: Creamer Media Reporter

  

Font size: - +

Name and Location
Bakubung platinum-group metals (PGMs) project, Bushveld Complex, South Africa.

Client
JSE-listed Wesizwe Platinum.

Project Description
The Bakubung platinum project, formerly known as the Frischgewaagd-Ledig project, will entail the construction of a PGM mine on Wesizwe Platinum's core assets, on the farm Frischgewaagd portions 3, 4 and 11, and on the farm Ledig portions 1 and 2.

The project will consist of an underground mine and a surface concentrator plant and takes into account the establishment of all surface infrastructure, servitudes for bulk power and water supply, the sinking and equipping of ventilation and main shafts, the associated underground infrastructure, the ancillary excavations and the access development to establish a footprint for full production.

The proposed access to the orebody will be through the sinking of an independent twin vertical-shaft system. This will comprise a 1 000-m-deep, 8.5-m-diameter downcast men-and-materials and hoisting shaft, as well as a 930-m-deep upcast ventilation shaft of 7.5 m diameter. The shafts will be strategically positioned to provide the most effective access to both reef horizons.

The mine is specifically designed for optimum flexibility in terms of mining method (conventional, mechanised or hybrid) and allows for fast production build-up to enhance shareholder value in the project.

The intention is to build the concentrator plant in three modules that are interchangeable between Merensky and upper group two (UG2) of initially 2 x Merensky and 1 x UG2, reversing this configuration when the mine becomes predominantly UG2 in the latter years of its production programme. This will allow for considerable flexibility in grading the different ores and ensure optimum PGM recoveries. The design includes a primary one-stage crushing into a semiautogenous mill with a mill-float-mill-float circuit.

The project has an estimated life-of-mine of 35 years at a production rate of 230 000 t/m, producing an average of 350 000 oz/y of platinum-group elements during steady state production. This production rate is a major improvement on the 180 000 t/m envisaged during the prefeasibility study stage and reflects the underlying quality and size of the orebody, as well as the extent of the proposed mine.

The mine will permanently employ 2 300 workers when in full production, of whom 120 would work at the process plant and 1 800 underground.

Value
The capital cost estimate for the project is forecast at R7.9-billion and with expected inflation and cost escalation, is expected to rise to R12-billion.

Duration
Main commissioning is scheduled for 2018 and full production is expected in 2023.

Latest Developments
JSE-listed Wesizwe Platinum’s new COO Paul Smith has said that he has confidence in the viability of the company’s flagship Bakubung platinum project, despite the volatile nature of South Africa’s platinum sector.

He notes that the project is being constructed on a virgin orebody that contains competitive ore grades, compared with other mines in the area, adds to its viability.

Meanwhile, construction of the project is on schedule and within budget.

The 30-m-high ventilation shaft, which was put up three weeks ago, is currently 170 m below ground with permanent sinking to start in March.

The first blast at the main shaft, which was carried out in September 2012, is currently 71 m deep and will eventually reach 1 km and reach a capacity of 230 000 t of ore and 40 000 t of waste a month.

The shaft’s headgear assembly is 70% complete and will be erected in May or June.  

The winder houses at both shafts were completed at the end of 2012, with commissioning of both shafts scheduled for the third quarter of 2018.

The 8 MW Phase 1 power supply for the project was completed at the end of January 2013, with Phase 2 to start soon. The second phase will supply Bakubung’s 66 MW power requirement when it reaches full production.

Looking ahead, Smith says Wesizwe’s focus will be to safely sink Bakubung’s shafts within budget and on schedule, while also turning its attention to other speciality metals.

Key Contracts and Suppliers
Qinisele Resources (corporate adviser); TWP Projects (feasibility study and contractor Phase 1); Scribante Construction (earthworks and civil work Phase 1); Benco Engineering (blasting); Blast Management & Consulting (blast monitoring); Eskom (power supply); Liviero (civil earthworks and concrete) and Aveng Grinaker-LTA Mining (shaft-sinking contract).

On Budget and on Time?
The project is on schedule and within budget.

Contact Details for Project Information
Wesizwe Platinum, tel +27 11 994 4600, fax +27 11 944 4601 or email manie@wesizwe.com; or company secretary Sirkien van Schalkwyk, email Sirkien@wesizwe.com; or spokesperson Tracey Peterson, cell +27 83 408 7173 or email tracey@simplysaid.co.za.
JNMC, tel +86 935 8811111 or fax +86 935 8811612.
Scribante Construction, tel +27 11 466 9232, fax +27 11 466 9233 or email office@scribanteconstruction.co.za.
TWP Projects, tel +27 11 218 3000, fax +27 11 218 3100 or email twpinfo@twp.co.za; or MD Digby Glover, email dglover@twp.co.za.
Aveng Grinaker-LTA, +27 11 578 6000 or fax +27 11 578 6161.

Edited by Creamer Media Reporter

Comments

Latest Multimedia

Latest News

Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.122 0.156s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: