Project Description
Back Forty has openpit proven and probable mineral reserves of 11.65-million tonnes grading 1.85 g/t gold, 21.7 g/t silver, 2.64% zinc, 0.21% lead and 0.28% copper.
Mining operations will encompass a large openpit that will be mined with conventional mining equipment in three pushback phases.
The mining fleet will comprise major equipment used directly in the rock-moving operation, including blast-hole drills, hydraulic excavators, and 91 t haul trucks. Various support equipment will be required, such as dozers, graders, water trucks, and light vehicles for maintenance, personnel transport and mine supervision.
The process plant design is based on a flexible metallurgical flowsheet designed for treating of a variety of ore types. The key project design criteria for the process plant are:
a nominal throughput of 4 000 t/d sulphide ore and 800 t/d oxide ore.
crushing circuit availability of 75%, which will be supported by surge bins and dedicated feeders for choke feeding cone crushers for optimum crushing performance and wear minimisation. The oxide and sulphide process plant will have availability of 91.3% using standby equipment in critical areas and reliable grid power supply.
sufficient automated plant control to minimise the need for continuous operator interface and allow for manual override and control if and when required.
The project has an estimated mine life of seven years, with total payable gold production of 468 000 oz (or an average of 67 000 oz/y) and 135 000 oz in Year 1. Total payable gold equivalent production of 1.1- million ounces.
Total payable zinc production is estimated at 512-million pounds (or an average of 73-million pounds a year). Total payable zinc equivalent production of 1.2-billion pounds is estimated.
Aquila has also identified several opportunities to further enhance the overall economics of the project, including the possible addition of an underground expansion.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 6% discount rate, of $208-million, and an internal rate of return 28.2%, with payback of 2.2-years.
Capital Expenditure
Initial project capital costs are estimated at $294-million.
Planned Start/End Date
The project has an estimated 24-month construction period.
Latest Developments
The state of Michigan has issued a final decision and order upholding the mining permit for Aquila's Back Forty zinc and gold project.
The Menominee Indian Tribe of Wisconsin and an individual owning property near the project site challenged the mining permit in 2017, but following hearings and testimony, a judge on May 3 ruled that the proposed mining operation would operate in compliance with the state’s nonferrous metallic mining statute.
Aquila has received all state and federal permissions required for the construction and start of operations at Back Forty.
Key Contracts and Suppliers
Lycopodium Minerals Canada (feasibility study).
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Aquila Resources director of corporate development and investor relations David Carew, tel +1 647 943 5677 or email dcarew@aquilaresources.com.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation