Atlatsa implements new development plan at Bokoni

31st March 2017

By: Megan van Wyngaardt

Creamer Media Contributing Editor Online

     

Font size: - +

JOHANNESBURG (miningweekly.com) – With the restructure plan at Atlatsa’s Bokoni mine having reached completion, resulting in the older UM2 and vertical Merensky shaft operations being placed on care and maintenance, Bokoni will now operate only two underground shafts, both of which are in ramp-up phases toward steady state.

The TSX- and JSE-listed company on Friday said the Middelpunt Hill UG2 shaft was currently operating at 80% of its targeted steady state volumes of 60 000 t/m and is estimated to reach steady state by the second quarter of 2018.

Further, the Brakfontein Merensky shaft was currently operating at 50% of its targeted steady state volumes of 90 000 t/m and it is estimated to achieve steady state by the second quarter of 2019.

“Management is currently implementing a comprehensive development plan to ensure sufficient stoping face length is made available to achieve the planned production ramp-up.

“This is being achieved by improving waste handling infrastructure and upgrading trackless mining equipment required for development. Management is also in the process of appointing a contract miner to develop critical ends to ensure that development targets are met,” the company said in a statement.

The mine has well-established infrastructure and ore is processed on site at the concentrator plant with an installed design capacity of 160 000 t/m.

The initial phase of the new operational plan at Bokoni is targeting a steady state operation of 145 000 t/m throughput being achieved by 2019, with volumes being processed through the existing concentrator plant.

Meanwhile, the company noted that discussions were continuing between Anglo American Platinum (Amplats), Atlatsa and relevant stakeholders surrounding an appropriate exit for Amplats from the Bokoni joint venture.

These discussions recognise that execution of the new operational plan is critical to ensure the future sustainability of the Bokoni operations, having regard to any potential future corporate activity surrounding Bokoni going forward.

PRODUCTION RESULTS
As a result of two shafts being placed on care and maintenance during 2016, the tonnes milled at Bokoni decreased by 21.4% to 1.31-million tonnes and the platinum group metals (PGMs) ounces produced decreased to 159 241, compared to 190 740 oz produced during 2015’s financial year.

Primary development decreased by 26.9% year-on-year to 5 686 m, owing to the impact of the restructuring. Implementation of the restructure plan resulted in a backlog in development during 2016 relative to the intended mine development plan. This backlog is being addressed as part of the new operational plan being implemented in 2017.

Recoveries at the concentrator plant increased by 0.9% to 89.5% and 1% to 86.7% for the Merensky and UG2 concentrate, respectively, as a result of an increase in throughput and processing of lower grade ore from the opencast operation.

Revenue decreased by 20.9% year-on-year to $162.7-million as a result of a decrease of 16.5% in PGM ounces produced and a 6.4% decrease in the average dollar platinum price per ounce from $1 054 in 2015 to $987 in 2016, partially offset by a 5.4% increase in the rand PGM basket price.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Projects

Image of lithium ore stockpile
Lithium conversion plant, Australia
Updated 2 hours 31 minutes ago By: Sheila Barradas
Aerial view of the Amapá mine
Amapá iron-ore project, Brazil
Updated 2 hours 31 minutes ago By: Sheila Barradas

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.587 0.64s - 312pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: