AngloGold Ashanti signs gas supply for Tropicana

21st July 2014

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Gold miner AngloGold Ashanti has inked an infrastructure agreement with natural gas infrastructure group APA Group for the transportation of natural gas to the Sunrise Dam and Tropicana gold mines, in Western Australia.

APA would construct a new 292 km pipeline which would connect its Goldfields Gas Pipeline through the lateral pipeline at the Murrin Murrin nickel mine, and extend it past Sunrise Dam to Tropicana.

Construction would start in February next year, and first gas at Tropicana was expected in January 2016.

The pipeline and associated infrastructure would be constructed for a total capital cost of A$140-million.

“Gas power generation is expected to reduce cash operating costs at both sites between A$25/oz and A$30/oz,” said AngloGold Ashanti senior VP for Australia Michael Erickson.

“The pipeline and gas transportation agreement will also provide continuity of fuel supply, reduce exposure to diesel price volatility and significantly reduce the number of trucks on the road, which has an important safety benefit, as well as reducing road maintenance costs.”

Erickson said that the natural gas was also a cleaner fuel and its use would reduce greenhouse-gas emissions at both mines.

The power stations at  Sunrise Dam and Tropicana would be modified in order to run on natural gas, with diesel to be used as a backup facility.

Edited by Creamer Media Reporter

Comments

Projects

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.132 0.164s - 90pq - 2rq
Subscribe Now