Alkane considers staged development of Dubbo to lower costs
PERTH (miningweekly.com) – Rare earths developer Alkane Resources has flagged a modular construction at its Dubbo zirconia project, in New South Wales.
Since the release of the front-end engineering design study last year, Alkane has been working to reduce the expected $0.93-billion capital cost of the Dubbo project. The company said on Friday that significant capital cost reductions could be achieved by constructing Dubbo in two stages of 500 000 t/y each.
The staged approach would also allow Alkane to continue to develop and grow the market for its products, while allowing a smaller commitment by counterparties that could grow as the project matured.
The second stage will be built after the first has been successfully commissioned and customer relationships and revenue streams have been established.
Alkane on Friday revealed the preliminary conceptual cost estimates for each stage, with the first stage likely to cost A$480-million with construction targeted to start in 2017 and complete in 2019.
The second stage, which will bring capacity to one-million tonnes a year, will cost an additional A$360-million, with construction targeted to start in 2022 and finish in 2023.
Alkane said that it would now progress the engineering of the Dubbo project on the basis of this design, and would pursue financing on the basis of the improved business case.
The Dubbo project is expected to extract 19.5-million tonnes of rare metals and rare-earth ores from an opencut mine, at a rate of one-million tonnes a year.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation