Abujar gold project, Côte d’Ivoire – update

Drill core from the Abujar gold mine

Photo by Tietto Minerals

14th July 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Abujar gold project.

Location
About 30 km from Daloa, a major regional city in central-western Côte d’Ivoire.

Project Owner/s
West African gold explorer and developer Tietto Minerals.

Project Description
The Abujar gold project comprises the Middle, South and North contiguous exploration tenements.

The project has total proven and probable minerals reserves of 34.4-million tonnes grading 1.3 g/t gold, and mineral resources of 87.5-million tonnes grading 1.2 g/t gold.

The project will source feed for the mill from the AG and APG deposits.

The AG deposit provides the majority of the value for the operation and the AG openpit comprises several openpits, all within 1 to 2 km of the proposed plant site, with several satellite pits located along strike to the north and south.

The definitive feasibility study (DFS), completed on the project in October 2021, proposes a conventional semiautogenous grinding milling circuit, and gravity and carbon-in-leach processing, with a throughput capacity of four-million tonnes a year for fresh ore and 4.8-million tonnes for oxide and transition blend once ramp-up is completed.

Tietto will examine the potential for the Abujar mill throughput to increase above DFS levels once the plant is operational as demonstrated by other West African projects.

Average gold production over the 11-year mine life is estimated at 1.7-million ounces.

Forecast gold production in the first year is estimated at 260 000 oz and 1.2-million ounces over the first six years.

A contractor will conduct openpit mining using conventional openpit mining techniques common in West Africa.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 5% discount rate, of $959-million and an internal rate of return of 155%, with an after-tax payback of nine months.

Capital Expenditure
Capital costs are estimated at $200-million, including contingencies.

Planned Start/End Date
First gold was poured in January 2023.

Latest Developments
Commercial production has been declared at the Abujar gold mine, less than 18 months after construction activities started.

Tietto produced 15 592 oz in the June quarter, after producing 9 500 oz in the March quarter.

Key Contracts, Suppliers and Consultants
EPSA (preferred tenderer for the openpit mining contract).

Contact Details for Project Information
Tietto Minerals, tel +61 8 9331 6710 or email admin@tietto.com.

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Latest News

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024

Showroom

Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.225 0.284s - 91pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: